Key Facts

Adopted code
International Plumbing Code, SC edition
Permit required
Install, alter, repair, replace plumbing systems
Exempt
Stopping leaks/clearing stoppages (§105.2)
Permit expires
Unused after 180 days (§105.5)
No permit before starting
Double fee under §108.4
Enforcing office
Charleston County Building Official

Summary

Unincorporated Charleston County adopts the International Plumbing Code under Sec. 4-16 (§101.4.5) for every plumbing installation, alteration and repair, and Sec. 4-20 (§105.1) requires the owner or contractor to apply to the Building Official and obtain a permit before that work begins.

City-specific rules exist: Charleston, and North Charleston have their own plumbing permits rules that differ from Charleston County's county-level regulations. If you live in one of those cities, check the city-specific page instead.

101.4.5 Plumbing. The provisions of the International Plumbing Code as adopted by the S.C. Building Codes Council shall apply to the installation, alteration, repair and replacement of plumbing systems, including equipment, appliances, fixtures, fittings and appurtenances, and where connected to a water or sewage system and all aspects of a medical gas system. ... 105.1 Required Permits. Any owner or authorized agent who intends to construct, enlarge, alter, repair, move, demolish, or change the occupancy of a building or structure, or to erect, install, enlarge, alter, repair, remove, convert or replace any electrical, gas, mechanical or plumbing system, the installation of which is regulated by "this code", or to cause any such work to be done, shall first make application; to the Building Official and obtain the required permit.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 21).

Full Breakdown

Sec. C. ' Sec. 1 folds plumbing into the same permit duty as building, electrical, gas and mechanical work: the owner or authorized agent must first apply to the Building Official and obtain the required permit before installing, altering, repairing or replacing a plumbing system. 1 lets the Building Official reject an incomplete or non-conforming application in writing. 2: stopping a leak in a drain, water, soil, waste or vent pipe without replacing concealed piping, and clearing a stoppage or repairing a fixture leak that does not require replacing or rearranging valves, pipes or fixtures; anything beyond that, including replacing a concealed defective pipe, is treated as new work requiring a permit and inspection. 5 if work is not started within 180 days or is abandoned for 180 days, subject to written extensions.

Violations & Fines

Plumbing work beyond the narrow leak-stopping and fixture-repair exemptions in §105.2, done without a permit, doubles the fee under Sec. 4-23 (§108.4) and is a misdemeanor under Sec. 4-30 (§115.1.1), with each day of continued violation a separate offense. The Building Official can also require the work to be exposed for inspection under Sec. 4-24 (§109.1) before it is approved.

Frequently Asked Questions

Do I need a permit to replace a water heater or repipe a bathroom in unincorporated Charleston County?
Yes. Sec. 4-20 (§105.1) requires a plumbing permit for installing, altering, repairing or replacing a plumbing system under the adopted International Plumbing Code (Sec. 4-16, §101.4.5); only minor leak-stopping and stoppage-clearing work that does not touch concealed piping is exempt under §105.2.
Is fixing a leaky faucet exempt from the plumbing permit rule?
Yes, if it is limited to clearing a stoppage or repairing a leak in a pipe, valve or fixture without replacing or rearranging valves, pipes or fixtures, per §105.2. Replacing a concealed defective pipe, though, is treated as new work needing a permit and inspection.
What if I install plumbing before getting a permit?
Sec. 4-23 (§108.4) doubles the permit fee for work commenced before issuance, and Sec. 4-30 (§115.1.1) makes the unpermitted regulated work a misdemeanor, with each additional day the violation continues counted as a separate offense.
Which plumbing code does the county actually enforce?
Sec. 4-16 (§101.4.5) adopts the International Plumbing Code as adopted by the South Carolina Building Codes Council, covering everything from fixture connections to medical gas systems, so county plumbing inspections follow that state-adopted edition.

Sources & Official References

Other rules in Charleston County

All Charleston County rules

Compare Charleston County to another location·View the South Carolina building safety overview

Get notified when Plumbing Permits in Charleston County, SC changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Plumbing Permits in Cities Across Charleston County