Key Facts

Permit required before
Installing, altering, or replacing plumbing
Kitchen faucet limit
1.8 gpm at 60 psi
Lavatory faucet limit
1.2 gpm at 60 psi
Showerhead limit
2.0 gpm at 80 psi
Toilet limit
1.28 gallons per flush
Water-efficiency ordinance
Ord. No. 011-24, eff. 7-16-24

Summary

Coweta County requires a permit before any plumbing system is installed, altered, or replaced, issued by the building official under Item 101.3.6 of the technical codes. Ordinance 011-24 also layered water-efficiency amendments onto the state plumbing code, capping fixture flow rates and setting design rules for new landscape irrigation systems.

These county ordinances apply to unincorporated areas of Coweta County. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

Plumbing. The provisions of the International Plumbing Code, as adopted and amended by the state Department of Community Affairs, shall apply to every plumbing installation, including alterations, repairs, replacement, equipment, appliances, fixtures, fittings and appurtenances, when connected to a water or sewerage system. ... On all buildings structures electrical, plumbing, mechanical and gas systems or alterations requiring a permit, a fee for each permit shall be paid as required at the time of filing application, in accordance with the schedule as established by the applicable governing authority. ... Showerhead. A shower head that allows a flow of no more than the average of 2.0 gallons of water per minute at 80 pounds per square inch of pressure, is listed in the WaterSense Specification for Showerheads, and meets the US Department Definition of Energy definition of showerhead.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 40).

Full Breakdown

1, the general permit rule that requires an owner, agent, or contractor to apply to the building official and obtain a permit before any such system is erected, altered, repaired, or replaced. 2 adds a citation for anyone who starts plumbing work before the permit issues. On top of the base International Plumbing Code, Sec. 14-33, adopted by Ord. No. 4, with narrow exceptions for blowout-design water closets, vegetable sprays, clinical sinks, laundry trays and service sinks, and emergency showers and eyewash stations. New landscape irrigation systems connected to the public water system, other than those for agriculture, golf courses, or served by a private water source, must include a rain sensor shut-off, a master shut-off valve near the point of connection, and pressure-regulating devices, and any system other than for a single-family home must add a WaterSense irrigation controller and at least one flow sensor that can detect high-flow leaks and shut the master valve.

Violations & Fines

Beginning plumbing work before the permit is issued draws a citation under Item 104.7.2 in addition to the required fee. A permit lapses under Item 104.1.7 if work is not begun within six months, is suspended six months after starting, or is not finished within twelve months, forcing a new application and payment of a renewal fee under Item 104.1.8.

Frequently Asked Questions

Do I need a permit for plumbing work in Coweta County?
Yes. Item 101.3.6 applies the International Plumbing Code to every plumbing installation connected to a water or sewer system, and Item 104.1.1 requires the owner, agent, or contractor to obtain a permit from the building official before any plumbing system is erected, altered, repaired, or replaced.
What's the maximum flow rate for a showerhead in Coweta County?
Table 604.4, adopted under Sec. 14-33, caps showerheads at an average of 2.0 gallons per minute at 80 psi, and the fixture must carry the WaterSense label and meet the U.S. Department of Energy's definition of a showerhead.
Does a new sprinkler system need special equipment in Coweta County?
If it connects to the public water system and isn't for agriculture, a golf course, or a private well, Sec. 14-33 requires a rain sensor shut-off, a master shut-off valve near the connection point, and pressure-regulating devices; systems other than single-family homes also need a WaterSense controller and a flow sensor.

Sources & Official References

Other rules in Coweta County

All Coweta County rules

Compare Coweta County to another location·View the Georgia building safety overview

Get notified when Plumbing Permits in Coweta County, GA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.