Coweta County, GA Building Safety: Plumbing Permits (2026)
Key Facts
- Permit required before
- Installing, altering, or replacing plumbing
- Kitchen faucet limit
- 1.8 gpm at 60 psi
- Lavatory faucet limit
- 1.2 gpm at 60 psi
- Showerhead limit
- 2.0 gpm at 80 psi
- Toilet limit
- 1.28 gallons per flush
- Water-efficiency ordinance
- Ord. No. 011-24, eff. 7-16-24
Summary
Coweta County requires a permit before any plumbing system is installed, altered, or replaced, issued by the building official under Item 101.3.6 of the technical codes. Ordinance 011-24 also layered water-efficiency amendments onto the state plumbing code, capping fixture flow rates and setting design rules for new landscape irrigation systems.
Plumbing. The provisions of the International Plumbing Code, as adopted and amended by the state Department of Community Affairs, shall apply to every plumbing installation, including alterations, repairs, replacement, equipment, appliances, fixtures, fittings and appurtenances, when connected to a water or sewerage system. ... On all buildings structures electrical, plumbing, mechanical and gas systems or alterations requiring a permit, a fee for each permit shall be paid as required at the time of filing application, in accordance with the schedule as established by the applicable governing authority. ... Showerhead. A shower head that allows a flow of no more than the average of 2.0 gallons of water per minute at 80 pounds per square inch of pressure, is listed in the WaterSense Specification for Showerheads, and meets the US Department Definition of Energy definition of showerhead.
Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 40).
Full Breakdown
1, the general permit rule that requires an owner, agent, or contractor to apply to the building official and obtain a permit before any such system is erected, altered, repaired, or replaced. 2 adds a citation for anyone who starts plumbing work before the permit issues. On top of the base International Plumbing Code, Sec. 14-33, adopted by Ord. No. 4, with narrow exceptions for blowout-design water closets, vegetable sprays, clinical sinks, laundry trays and service sinks, and emergency showers and eyewash stations. New landscape irrigation systems connected to the public water system, other than those for agriculture, golf courses, or served by a private water source, must include a rain sensor shut-off, a master shut-off valve near the point of connection, and pressure-regulating devices, and any system other than for a single-family home must add a WaterSense irrigation controller and at least one flow sensor that can detect high-flow leaks and shut the master valve.
Violations & Fines
Beginning plumbing work before the permit is issued draws a citation under Item 104.7.2 in addition to the required fee. A permit lapses under Item 104.1.7 if work is not begun within six months, is suspended six months after starting, or is not finished within twelve months, forcing a new application and payment of a renewal fee under Item 104.1.8.
Frequently Asked Questions
Do I need a permit for plumbing work in Coweta County?
What's the maximum flow rate for a showerhead in Coweta County?
Does a new sprinkler system need special equipment in Coweta County?
Sources & Official References
Other rules in Coweta County
Compare Coweta County to another location·View the Georgia building safety overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.