Fort Lauderdale, FL Building Safety: Plumbing Permits (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Governing section
Code of Ordinances Sec. 28-54(a)
Who must permit
Licensed plumber for building-to-lateral connections
Required documents
Certificate of competency plus insurance certificate
Plans required
Signed, sealed engineer drawings before permit
Inspection
Supervised by the city plumbing inspector
Connection standard
Must be gastight, watertight, rootproof

Summary

Fort Lauderdale requires a licensed plumber connecting a building's sewer line to the sanitary sewer lateral on private property to file for and obtain a plumbing permit from the development services department, along with a certificate of competency and proof of insurance, under Code of Ordinances Sec. 28-54(a).

(a)It shall be required of every licensed plumber who seeks to perform sewer installation from the building sewer to the sanitary sewer laterals on private property to file and obtain a plumbing permit with the development services department (DSD) and provide a certificate of competency and insurance certificate.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 67 Update 1 | Unified Land Development Code: Supplement 58 Update 2).

Full Breakdown

Sec. 28-54 sits within the city's sanitary sewer connection rules and splits sewer permitting by trade: a licensed plumber must obtain a plumbing permit before connecting the building sewer to the sanitary sewer lateral on private property, while a licensed underground utility and excavation contractor, engineering contractor, or approved general contractor must instead obtain an engineering permit before installing sewer manholes, gravity mains, lift stations, force mains or laterals that connect to gravity mains. Both permit types require the applicant to provide a current certificate of competency and an insurance certificate to the development services department before work begins.

This division-of-labor rule reinforces Sec. 28-53, which likewise restricts sewer connection work on private property to a duly licensed and certified plumber, restricts main and lateral installation to a licensed underground utility, excavation, or engineering contractor, and requires asphalt pavement restoration to be handled by a licensed engineering or paving contractor. Before any permit issues, Sec. 28-52 requires scaled drawings, details and specifications signed and sealed by a Florida registered professional engineer for review by development services department and public works engineering division staff, and no sewer work of any kind may begin until plans are approved and the permit is issued.

Once work is complete, Sec. 28-55 requires the applicant to notify development services when the building sewer is ready for inspection, and the connection to the sanitary sewer system must be made under the supervision of the plumbing inspector and must be gastight, watertight and rootproof.

Violations & Fines

Performing sewer connection work without the required plumbing or engineering permit, or without the licensed trade the work calls for under Sec. 28-53, is a violation of the sewer connection rules regardless of whether the underlying plumbing itself is done correctly. Sec. 28-52 further bars starting any sewer work before plans are approved and the permit issued, and connections made without the plumbing inspector's required supervision can be rejected at final inspection under Sec. 28-55.

Frequently Asked Questions

Who needs a plumbing permit for sewer work in Fort Lauderdale?
Any licensed plumber connecting a building's sewer line to the sanitary sewer lateral on private property must file for and obtain a plumbing permit from the development services department under Sec. 28-54(a), along with a certificate of competency and an insurance certificate. Installing gravity mains, manholes or lift stations instead requires an engineering permit from a different licensed trade.
Can I install my own sewer connection in Fort Lauderdale?
No. Sec. 28-53 requires that connecting a building sewer to the sanitary sewer lateral on private property be performed by a duly licensed and certified plumber, and separately licensed contractors are required for main, lift station and lateral installation work. A homeowner cannot self-perform this connection work.
What has to happen before a sewer connection is inspected?
Under Sec. 28-55, the applicant must notify the development services department when the building sewer is ready, and the connection to the sanitary sewer system has to be made under the plumbing inspector's supervision. The finished connection must be gastight, watertight and rootproof, and any deviation from the approved procedure or materials needs prior approval.

Sources & Official References

Other rules in Fort Lauderdale

All Fort Lauderdale rules

Florida rules heatmap·Compare Fort Lauderdale to another location·View the Florida building safety overview

Get notified when Plumbing Permits in Fort Lauderdale, FL changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Plumbing Permits in Nearby Cities

How other cities in Broward County handle plumbing permits.

Pompano Beach, FL
Some Restrictions