Skip to main content
CityRuleLookup

McHenry County, IL Building Safety: Plumbing Permits (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Governing code
Illinois State Plumbing Code, 77 Ill. Adm. Code §890+
Local amendments
None; adopted without addition or modification
Conflict rule
Plumbing code prevails over other county codes
Permit issuer
Department of Planning and Development
Permit validity
2 years; work must start within 180 days
Scope
Installation, alteration, repair, replacement, medical gas systems

Summary

Plumbing work anywhere in unincorporated McHenry County is governed by the Illinois State Plumbing Code, 77 Ill. Adm. Code §§ 890 et seq., adopted by the County Board word-for-word with no local amendments. The state code prevails over any conflicting county rule, and permits for covered plumbing work run through the Department of Planning and Development under the same Title 15 building-permit framework.

These county ordinances apply to unincorporated areas of McHenry County. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

§ 15.24.010 ADOPTED. The Illinois State Plumbing Code, 77 Ill. Adm. Code §§ 890 et seq., as amended from time to time, is hereby adopted by reference in its current form, without addition, modification, exception or amendment. § 15.24.020 CONFLICT WITH OTHER CODES. If there is any conflict between this code and other codes adopted by the County, the Illinois State Plumbing Code provision shall prevail.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: 2025 S-5: Supplement contains: Local legislation current through Ord. A25-0037, passed 8-19-2025 | State legislation current through ALS 2025 Pamphlet No. 1).

Full Breakdown

McHenry County does not write its own plumbing code: unincorporated territory operates entirely under the Illinois State Plumbing Code, 77 Ill. Adm. Code §§ 890 et seq., which the County Board adopted by reference "without addition, modification, exception or amendment" (§ 15.24.010). Many county code chapters carry local tweaks; plumbing does not, so contractors working outside city limits pull permits against the state text exactly as written, not a McHenry-specific variant. Where any other adopted county code, including the local International Building Code amendments, conflicts with the state plumbing rules, § 15.24.020 makes the Illinois Plumbing Code the controlling authority.

The link to the building permit process runs through the county's amended IBC 101.4.3, which assigns "installation, alteration, repair and replacement of plumbing systems, including equipment, appliances, fixtures, fittings and appurtenances, and where connected to a water or sewage system and all aspects of a medical gas system" to the plumbing code, while routing private sewage disposal and private wells to the separate Public Health Ordinance. In practice, the Department of Planning and Development takes the permit application on its own form (§ 15.04.010, IBC 105.3), and once issued a permit is good for two years but becomes invalid if work is not started within 180 days or is suspended for 180 days; the building official is authorized to grant written extensions of up to 180 days at a time for justified cause (IBC 105.5).

Violations & Fines

Chapter 15.24 sets no plumbing-specific fine; enforcement runs through the same building-code framework that issues the permit. Plumbing work performed without the required Department of Planning and Development permit, or installed contrary to the adopted state code, exposes the property to the county's general building-code enforcement path, including a stop-work order from the building official and referral for corrective action under Title 15.

Frequently Asked Questions

Do I need a permit for plumbing work in unincorporated McHenry County?
Yes. Plumbing installation, alteration, repair and replacement covered by the Illinois State Plumbing Code requires a permit from the Department of Planning and Development, filed on the department's own application form under the county's Title 15 building-permit process (§ 15.04.010, IBC 105.3).
Which plumbing code applies outside McHenry County's cities?
The Illinois State Plumbing Code, 77 Ill. Adm. Code §§ 890 et seq., which the County Board adopted "without addition, modification, exception or amendment" under § 15.24.010. There is no separate McHenry County plumbing chapter with local technical changes.
What happens if county rules conflict with the state plumbing code?
Section 15.24.020 resolves it directly: whenever another adopted county code conflicts with the plumbing rules, "the Illinois State Plumbing Code provision shall prevail." That includes conflicts with the county's own amended International Building Code.
How long is a McHenry County plumbing permit good for?
Two years from issuance under the county's IBC 105.5 amendment. The permit still lapses earlier if the authorized work is not started within 180 days, or is stopped for 180 days, though the building official is authorized to grant written extensions of up to 180 days for justified cause.

Sources & Official References

Other rules in McHenry County

All McHenry County rules

Compare McHenry County to another location·View the Illinois building safety overview

Get notified when Plumbing Permits in McHenry County, IL changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.