Skagit County, WA Building Safety: Plumbing Permits (2026)
Key Facts
- Plumbing code
- 2021 IAPMO Uniform Plumbing Code, SCC 15.04.020(4)
- Excluded chapters
- UPC Chapters 12 and 14 not adopted
- Also excluded
- UPC venting/combustion-air rules, building sewer sections
- Permit expiration
- Stand-alone plumbing permit voids in 6 months
- Appeals
- SCC 14.06.150 process, no separate Board of Appeals
Summary
Unincorporated Skagit County plumbing work runs on the 2021 IAPMO Uniform Plumbing Code, adopted by SCC 15.04.020(4) with several chapters carved out, and a stand-alone plumbing permit issued under Title 15 expires in six months if the work is not completed, per SCC 15.04.030(1)(d).
(4) IAPMO Uniform Plumbing Code, 2021 Edition, published by the International Association of Plumbing and Mechanical Officials, together with supplements and amendments thereto; Appendices A, B, I and M; provided, that Chapters 12 and 14 are not adopted; provided further, that those requirements of the IAPMO Uniform Plumbing Code relating to venting and combustion air of fuel fire appliances as found in Chapter 5 and those portions of the Code addressing building sewers are not adopted. ... 4. Every stand-alone mechanical, plumbing, and demolition permit issued by the Building Official under the provisions of this code will expire by limitation and become null and void if the work authorized by such permit is not completed in accordance with the permitted requirements within six months from the date of issuance.
Full Breakdown
SCC 15.04.020(4) adopts the 2021 Edition of the IAPMO Uniform Plumbing Code, published by the International Association of Plumbing and Mechanical Officials, as the plumbing code for unincorporated Skagit County, together with Appendices A, B, I and M. The county does not adopt the Code's Chapters 12 and 14, and it drops the Uniform Plumbing Code's own venting and combustion-air rules for fuel-fired appliances in Chapter 5 as well as its provisions on building sewers, deferring instead to the county's separately adopted Mechanical and Fire Codes and its on-site sewage rules in SCC Chapter 12.48.
SCC 15.04.020(9) separately adopts the IAPMO Uniform Green Plumbing and Mechanical Code Supplement 2012 Appendix B for potable rainwater catchment systems. Permits for plumbing work follow Title 15's general permit-expiration rule as amended for stand-alone trades: under SCC 15.04.030(1)(d)4, a stand-alone mechanical, plumbing, or demolition permit expires and becomes void if the permitted work is not completed within six months of issuance, a shorter window than the three-year term given to a general building permit. Fees for plumbing permits are set under the Planning and Development Services fee schedule adopted by separate Board of Commissioners resolution, the same fee-setting mechanism SCC 15.04.030 uses for building permit fees generally.
Violations & Fines
Plumbing work performed without the required permit, or a stand-alone plumbing permit left open past its six-month window under SCC 15.04.030(1)(d)4, is enforced by the Skagit County Building Official under Title 15; a lapsed permit voids the authorization and requires a new permit application, with any Building Official decision appealable through the SCC 14.06.150 process rather than a separate board of appeals.
Frequently Asked Questions
What plumbing code applies in unincorporated Skagit County?
How long does a Skagit County plumbing permit stay valid?
Does Skagit County regulate rainwater catchment plumbing?
Sources & Official References
Other rules in Skagit County
Compare Skagit County to another location·View the Washington building safety overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.