Key Facts

Permit issuer
City of Twin Falls
Fee
Schedule fixed by city council resolution, paid at application
Early-start exception
Licensed plumber, work costing $500.00 or less
Official inspection
Within 60 days after notification
Adopted code
Idaho plumbing code as amended by the Idaho plumbing board
Penalty
Misdemeanor, $1,000.00 fine or up to 6 months in jail

Summary

In the City of Twin Falls, Idaho, no one can construct, install, improve, extend or alter any plumbing system, or service lines to it, without first getting a permit from the City. A licensed plumber can start work after applying when the cost does not exceed $500.00, and the city adopts the Idaho plumbing code.

It shall be unlawful for any person, firm, copartnership, association or corporation to do, or cause or permit to be done, whether acting as principal, agent or employee, any construction, installation, improvement, extension or alteration of any plumbing system in any building, residence or structure, or service lines thereto without first procuring a permit from the city of Twin Falls authorizing such work to be done. Provided, a licensed plumber is hereby authorized, after making application for permit and pending receipt of permit, to proceed and complete improvements or alterations to plumbing systems, when the cost of said improvement or alteration does not exceed the sum of five hundred dollars ($500.00). Inspection of such work shall be the responsibility of the permit holder pending an official inspection, which shall be made within sixty (60) days after notification of inspection.

Full Breakdown

Section 4-3-2 of the Twin Falls City Code makes it unlawful for any person, firm, copartnership, association or corporation, acting as principal, agent or employee, to do or permit any construction, installation, improvement, extension or alteration of any plumbing system in any building, residence or structure, or service lines to it, without first procuring a permit from the city of Twin Falls. The one head start is for a licensed plumber, who after making application and pending receipt of the permit can proceed and complete improvements or alterations when the cost does not exceed five hundred dollars ($500.00).

Inspection of that work is the responsibility of the permit holder pending an official inspection, which is made within sixty (60) days after notification of inspection. Section 4-3-1 adopts the Idaho plumbing code, as it is amended, revised, compiled and published from time to time and as amendments are adopted by the Idaho plumbing board, as the official plumbing code for the city of Twin Falls. Under section 4-3-3 the applicant pays the permit fee at the time of application, in accordance with the schedule fixed by resolution of the city council.

Section 4-3-4 reaches anyone who practices plumbing without a certificate of competency or without registration, performs work without a permit, or refuses a lawful order of the building official. Section 4-1-2 also amends section R105.2 of the international residential code to delete the last two paragraphs beginning with "The stopping of leaks..." and "The clearing of stoppages..." in their entirety.

Violations & Fines

Under section 4-3-4, working without a permit, practicing plumbing without a certificate of competency or registration, violating any provision of the code, or failing to obey a lawful order of the building official within the prescribed time is a misdemeanor. The penalty is a fine of $1,000.00, imprisonment in the county jail for up to six (6) months, or both, and each violation is a separate offense.

Frequently Asked Questions

What plumbing work needs a permit in Twin Falls?
Section 4-3-2 covers any construction, installation, improvement, extension or alteration of any plumbing system in any building, residence or structure, or service lines to it. A permit from the City of Twin Falls must come first. The only head start is for a licensed plumber who has applied, on work costing no more than five hundred dollars ($500.00).
Which plumbing code applies in Twin Falls?
Section 4-3-1 adopts the Idaho plumbing code as the official plumbing code for the city of Twin Falls. The adoption follows the code as it is amended, revised, compiled and published from time to time, and as amendments or revisions are adopted by the Idaho plumbing board. The city does not print a separate local plumbing standard in that section.
How is the plumbing permit fee set?
Section 4-3-3 requires the applicant to pay the city a permit fee at the time of application, in accordance with the schedule fixed by resolution of the city council. The code chapter does not print dollar amounts, so the current figure comes from that council resolution rather than from the city code text.
When does the city inspect plumbing done under the $500 exception?
Under section 4-3-2, inspection of work a licensed plumber completes while the permit is pending is the responsibility of the permit holder pending an official inspection. The official inspection is made within sixty (60) days after notification of inspection. The exception applies only when the cost of the improvement or alteration does not exceed five hundred dollars ($500.00).

Sources & Official References

Other rules in Twin Falls

All Twin Falls rules

Compare Twin Falls to another location·View the Idaho building safety overview

Get notified when Plumbing Permits in Twin Falls, ID changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.