Jefferson County, MO Building Setbacks & Zoning: Lot Coverage Limits (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified August 2026

Key Facts

Impervious coverage cap
80% of the development site
Applies to
industrially-zoned unincorporated development
FAR limit
per Table 5-2, Article V
Residential buffer setback
50 feet from residential property
Encouraged surfaces
porous concrete or asphaltic paving

Summary

For industrially-zoned development in unincorporated Jefferson County, impervious surface (buildings, pavement) may cover up to 80% of the development site under the Industrial Design Standards, with porous paving encouraged for the remainder.

These county ordinances apply to unincorporated areas of Jefferson County. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

D. Site Coverage. 1. Maximum FAR (see Table 5-2 of Article V). The FAR shall be applied only to the area proposed for initial development, not to area left undeveloped and reserved for future expansion. 2. Impervious area coverage may extend up to eighty percent (80%) of the development site. Porous surfaces that allow storm water to infiltrate below the surface, such as porous concrete or asphaltic materials, are encouraged.

Full Breakdown

2400(D) of the Unified Development Order, part of Division 6 (Industrial Design Standards) within Article VII, governs site coverage for industrially zoned parcels in the unincorporated county. Two limits apply together: a maximum Floor Area Ratio (FAR) taken from Table 5-2 of Article V, applied only to the area actually proposed for initial development rather than land reserved for future expansion, and a separate impervious-area ceiling of 80% of the development site. The County encourages porous concrete or asphaltic surfaces that let stormwater infiltrate rather than run off, though the code does not mandate them.

2400(E)(1)-(2)). These industrial design standards apply only to developments in industrial zoning districts; they do not set a general residential or commercial lot-coverage cap for the rest of the county, which is governed by the setback and yard tables tied to each individual zoning district instead.

Violations & Fines

The UDO does not attach a standalone penalty to Section 400.2400. Because no specific penalty is provided, a coverage violation falls under the Code's General Penalty, Section 100.030: a fine of up to $1,000, imprisonment in the County Jail up to one year, or both, with each day the violation continues charged as a separate offense, prosecuted in Jefferson County Municipal Court.

Frequently Asked Questions

How much of an industrial lot in Jefferson County can be paved or built over?
Up to 80% of the development site can be impervious surface under Section 400.2400(D), covering buildings, parking, and pavement combined, though a separate Floor Area Ratio limit from Table 5-2 also applies to the building footprint itself.
Does the 80% impervious cap apply to residential lots too?
No. This standard sits in Division 6, Industrial Design Standards, and applies specifically to industrially zoned development in the unincorporated county; residential and commercial lot dimensions are governed by the setback and yard tables for each individual zoning district.
Is porous pavement required to meet the coverage limit?
No, it is encouraged but not mandated. Section 400.2400(D)(2) states porous surfaces that let stormwater infiltrate, such as porous concrete or asphaltic materials, are encouraged, but the 80% figure is a hard ceiling regardless of paving material.

Sources & Official References

Other rules in Jefferson County

All Jefferson County rules

Compare Jefferson County to another location·View the Missouri building setbacks & zoning overview

Get notified when Lot Coverage Limits in Jefferson County, MO changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.