Lead Paint
Norwalk outright bans lead paint on interior surfaces of any rental dwelling, rooming unit or fixture in a place occupied by children, covering windowsills, doors, walls, ceilings and stair rails, as part of the Housing Code's minimum standards for occupancy.
Norwalk Interior Lead Paint Prohibition
Heavy RestrictionsNorwalk Code § 59-4G
Lead paint or potentially hazardous material on the interior surfaces of any dwelling unit, rooming unit, rooming house or on any fixtures or other objects used, installed or located in or upon any exposed surface in any such facility subject to letting or occupancy by children is prohibited. Such interior surfaces include, but are not limited, to windowsills, window frames, doors, door frames,...
Building Permits
Norwalk requires a building permit before any construction, demolition, or building-moving work begins, with the fee set by the Board of Building Fee Review under § 26-8 and covering any electrical, plumbing, oil-burner, or gas-piping work folded into the same job. Starting work before the permit issues triggers a separate investigation fee of at least $200 on top of the permit fee itself.
Norwalk Building Permit Requirement
Some RestrictionsNorwalk Code § 26-6
A. Before receiving a building permit for construction, demolition or moving, the owner or his agent shall pay the fees provided for in § 26-8 hereof. Fees for permits are refundable in accordance with the State Building Code Section 114.5. Permit fees include the fees for permits for electrical, oil-burner installation, plumbing and gas-piping work included in the permitted construction, demol...
Electrical Permits
Norwalk charges a separate permit fee for electrical work under § 26-7B, whether that work is bundled into a building permit or done independently. The fee is set per circuit, with an added charge for every two circuits beyond the first two plus outside underground wiring, and any new service installation, repair, or replacement also needs its own permit and fee before work begins.
Norwalk Electrical Work Permit Fees
Some RestrictionsNorwalk Code § 26-7
§ 26-7. Additional fees. Permit fees for plumbing, electrical, oil-burner installation and gaspiping work done independently and not part of work under a building permit described below in subsections dealing with these trades shall be established pursuant to § 26-8 hereof. ... B. Electrical installations. (1) A fee shall be charged and paid for each permit or certificate of approval for an ele...
Plumbing Permits
Norwalk does not issue a separate building permit for plumbing work done on its own; instead the Building Inspector charges a fee for every fixture or receptacle that drains into the system. Sewer connections are different: they always need a permit and fee, and crews cannot backfill the trench until the Building Inspector signs off.
Norwalk Plumbing Permit and Fixture Fees
Some RestrictionsNorwalk Code § 26-7A
A. Plumbing. (1) For plumbing work there is no building permit; a fee shall be charged for each fixture or receptacle intended to receive and discharge water, liquid or water-carried wastes into a drainage system with which they are connected. ... (3) Sewer connections. All connections to the City sewer system, including repairs to any existing private line now connected to said-City sewer, sha...
Building Inspections
Norwalk routes every building project through the Department of Code Enforcement, which administers the entire path from permit application to certificate of occupancy. The Building Official and assistants must make all necessary inspections and enforce the State Building Code before any structure can be occupied.
Norwalk Building Permit and Inspection Process
Some RestrictionsNorwalk Code § 35A-2 and § 26-5
The Department shall be responsible for the administration of the entire building permit process and inspection procedure to provide an orderly transition from a building permit application to the issuance of a certificate of occupancy... The Building Official and assistants shall devote their whole time to the duties of their office, shall exercise supervision over the construction, alteration...