Building Permits

Waterbury requires a Building Official-issued permit before starting construction, alteration, addition or excavation on any building or structure, with mandatory multi-department review, a Class A-2 survey plot plan, and a six-month deadline to begin work or the permit lapses.

Waterbury Building Permit Requirements

Some Restrictions

Waterbury Code of Ordinances § 150.06

It shall be unlawful to commence construction, alteration or addition of any building, or excavation for any building, structure or use, until the application and plans therefor have been approved by the Building Official and a permit therefore has been issued in accordance with this section. All building permits shall require a formal application in writing. No permit shall be issued to an app...

Electrical Permits

Before any electrical wiring, system alteration or addition goes into a Waterbury building, the owner or contractor must secure a permit from the city's Electrical Inspector. Only a state-licensed electrician may apply, and the Inspector can decline to act on an application immediately. Fees are set annually in the city's budget fee schedule, not fixed in the ordinance itself.

Waterbury Electrical Work Permit Required

Some Restrictions

Waterbury Code of Ordinances § 151.12

(A) No electrical system or electric wiring shall be installed or repaired within or on any building or structure, nor shall any alteration or addition be made to any such existing system before a permit therefor shall first be secured from the Electrical Inspector. (B) Application for the permit, describing the work to be done, shall be made in writing to the Electrical Inspector by a pers...

Plumbing Permits

Waterbury requires a written permit from the City Engineer before any drainage or plumbing work begins on a building. A licensed plumber must apply in advance, describing the work, its location and start date, and cannot start until the permit is issued.

Waterbury Plumbing Permit Requirements

Some Restrictions

Waterbury Code of Ordinances § 156.20

Before proceeding to construct any portion of the draining system of any building, the plumber shall make written application to the City Engineer describing the work contemplated, where located and when same is to be commenced. This description of work shall be made in accordance with the provisions of this chapter to the satisfaction of the City Engineer, who shall then give a written permit ...

Building Inspections

Waterbury requires the permit holder for any electrical work to request inspection directly from the Electrical Inspector, filing notice between one and three business days before the desired inspection date, before a certificate of approval can be issued.

Waterbury Electrical Inspection Request Rules

Some Restrictions

Waterbury Code of Ordinances § 151.14

Whenever any electric wiring or installation or portion thereof is ready for inspection a request for the inspection shall be made to the Electrical Inspector, giving him the number of the electrical permit and any other information necessary to identify the work being performed. Every request for an inspection shall be made by the person to whom the permit was issued. Every notice for inspecti...