Key Facts

Governing amendment
UZO Amendment 123, adopted Nov. 3, 2025
Sunset date
Large Data Center use expires Nov. 30, 2026
Large Data Center threshold
Over 10,000 sq ft gross floor area
Data Center threshold
10,000 sq ft or less, no sunset
Zoning violation fine
$50 to $1,500 per day, § 6-3-1(d)
Administering body
Area Plan Commission / Board of Zoning Appeals

Summary

Tippecanoe County added a "Large Data Center" zoning category through UZO Amendment 123, adopted November 3, 2025, but built in its own expiration date. Footnote 75 to the Permitted Use Table says the category itself "shall cease to exist" on November 30, 2026, turning the current permission into a one-year placeholder while the Area Plan Commission works out permanent siting rules.

These county ordinances apply to unincorporated areas of Tippecanoe County. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

LARGE DATA CENTER. A physical facility composed of one or more buildings totaling over 10,000 square feet of gross floor area housing networked computer servers used for data storage and processing, along with related supportive equipment including but not limited to backup power generators and cooling devices. (Amend 123) ... 75. This land use category shall cease to exist in the Permitted Use Table as of November 30, 2026. (Amend. 123)

View official code

Official source re-checked September 8, 2026: the cited page had not changed since it was quoted.

Full Breakdown

Amendment 123 to the Tippecanoe County Unified Zoning Ordinance created the county's first data-center-specific zoning category, adopted November 3, 2025 in Tippecanoe County, Lafayette and West Lafayette, and adopted by lack of action in Battle Ground, Clarks Hill and Dayton on January 15, 2026. The amendment split the use into two definitions at UZO Section 1-10-2: a "Data Center" tops out at 10,000 square feet of gross floor area, while a "Large Data Center" is any facility of one or more buildings totaling over 10,000 square feet housing networked computer servers, backup generators and cooling equipment.

" That built-in expiration functions as a one-year moratorium on the interim rules. Unless the APC adopts a further amendment before the deadline, large data centers drop off the list of permitted uses entirely, and any new project after that date would need a rezoning or a special exception from the Area Board of Zoning Appeals rather than a by-right or conditional permit. The smaller "Data Center" category, covering facilities of 10,000 square feet or less, carries no sunset clause and stays permitted. The rule reaches the unincorporated county and the APC's partner towns, since all of them share the same UZO text.

Violations & Fines

The UZO's general enforcement section, 6-3-1, treats any structure or use maintained in violation of the ordinance as a common nuisance and sets fines of $50 to $1,500 for each violation, with every day of noncompliance counted as a separate violation. The Area Board of Zoning Appeals or the Administrative Officer can sue to force removal of the use, recover attorney's fees and court costs, and block any new permit application on the property until the violation is resolved.

Frequently Asked Questions

Can a large data center be built in Tippecanoe County right now?
Yes, through 2026. Amendment 123 lists "Large Data Center" as a permitted use, tagged Special Condition 4, in the county's designated zones under UZO Section 3-2's Permitted Use Table, so a project filed before the category expires can still go through the normal review process.
What happens to the large data center use category after November 30, 2026?
Footnote 75 to UZO Section 3-2 says the Large Data Center land use category "shall cease to exist in the Permitted Use Table" on that date. Unless the Area Plan Commission adopts a replacement ordinance first, any new project would need a rezoning or a special exception from the Board of Zoning Appeals instead of a by-right permit.
How does the county define a "Large Data Center"?
UZO Section 1-10-2 defines it as a physical facility of one or more buildings totaling over 10,000 square feet of gross floor area, housing networked computer servers used for data storage and processing along with supportive equipment such as backup power generators and cooling devices. A facility at or under that footprint is classified as a "Data Center" instead.
Does this sunset date apply in Lafayette and West Lafayette too?
Yes. The Unified Zoning Ordinance is shared by the Area Plan Commission's member jurisdictions. Amendment 123 took effect November 3, 2025 in Tippecanoe County's unincorporated area, Lafayette and West Lafayette, and by lack of action on January 15, 2026 in Battle Ground, Clarks Hill and Dayton, so the same expiration date applies countywide.

Sources & Official References

Other rules in Tippecanoe County

All Tippecanoe County rules

Compare Tippecanoe County to another location·View the Indiana data centers & crypto mining overview

Get notified when Data Center Moratoriums in Tippecanoe County, IN changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.