Everett, MA Data Centers & Crypto Mining: Data Center Zoning & Siting (2026)

Significant Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified October 2026

Key Facts

District covered
Everett Docklands Innovation District, Subdistricts A and B
Data Center use table row
Y, Y, SP, SP, SP, SP
Special Permit Granting Authority
Planning Board
Non-master maximum height
65 ft; master plan projects 370 ft with FAA limit
FAR, non-master uses
1.0, increased to 4.0 by special permit
Rooftop equipment screens
Excluded from height up to 40 feet, 10 feet from roof edge
Section added
10-28-2024 by Ord. No. C0260-24

Summary

In the City of Everett, Massachusetts (Middlesex County), the Zoning Ordinance lists a Data Center as a use in the Everett Docklands Innovation District under Section 37. A project outside a Master Plan Special Permit needs a special permit from the Planning Board in Subdistrict A and Subdistrict B, at any size. Nothing in that table makes it a by-right use.

a) Master Plan Developments: ... "Y" indicates that the Planning Board may, in its discretion, permit a use as part of the Master Plan Special Permit. Any use of such land must be specifically identified and approved in such Master Plan Special Permit. ... b) Non-Master Plan Developments: "Y" indicates that the use is allowed by right in the district. ... USE CATEGORY Master Planned Uses Non-Master Planned Uses Less Than 5,000 sq ft of Gross Floor Area Non-Master Planned Uses Greater Than 5,000 sq ft of Gross Floor Area RESIDENTIAL Sub A Sub B Sub A Sub B Sub A Sub B ... INNOVATION ... Data Center Y Y SP SP SP SP ... Data Center: Data Center shall mean a use involving a building/premise in which the primary use is occupied by computers and/or telecommunications and related equipment, including supporting equipment, where information is processed, transferred and/or stored.

Full Breakdown

Section 37 of the Everett Zoning Ordinance, added on 10-28-2024 by Ord. No. C0260-24, governs the Everett Docklands Innovation District, the EDID. The district has 2 subdistricts, Subdistrict A and Subdistrict B. Under the INNOVATION heading of the use table, the row for Data Center reads Y, Y, SP, SP, SP, SP. The six columns are Master Planned Uses, Non-Master Planned Uses Less Than 5,000 sq ft of Gross Floor Area, and Non-Master Planned Uses Greater Than 5,000 sq ft of Gross Floor Area, each split into Sub A and Sub B.

The ordinance defines the term in subsection (e)(4): a use involving a building or premise in which the primary use is occupied by computers and telecommunications and related equipment, including supporting equipment, where information is processed, transferred or stored. For a Master Plan Development, Y means the Planning Board can, in its discretion, permit the use inside a Master Plan Special Permit, and the use must be specifically identified and approved there. For non-master-planned projects the mark is SP, and the Planning Board is the Special Permit Granting Authority. A Y for a non-master development would mean by right, but the Data Center row never carries one.

The EDID dimensional table gives non-master-planned uses a 10 ft. front yard, a 10 ft. side yard, a 20 ft. rear yard, a maximum height of 65 ft, and FAR of 1.0, which can be increased to 4.0 by special permit. Master Plan Special Permit projects list a maximum height of 370 ft, with a footnote tying that figure to the height that complies with FAA and Massport critical airspace limits. Rooftop screens, fully enclosed mechanical penthouses or fences erected to conceal equipment are excluded from the height calculation up to 40 feet, if set back a minimum of 10 feet from the roof edge. The parking table has no Data Center row, and its "All other uses" line leaves the figure to the Building Commissioner.

Violations & Fines

Section 37 prints no penalty clause of its own. A data center that is not identified in an approved Master Plan Special Permit, or approved by special permit from the Planning Board where the table shows SP, is not an allowed use in the district. The Building Commissioner classifies unlisted uses and notes the classification on the building permit.

Frequently Asked Questions

Where in Everett, Massachusetts can a data center be built?
The printed use table that lists Data Center is the one for the Everett Docklands Innovation District in Section 37 of the Zoning Ordinance. There it is a Planning Board decision: Y inside a Master Plan Special Permit, SP for everything else, in both Subdistrict A and Subdistrict B. It is not marked by right anywhere in that table.
How does the ordinance define a data center?
Subsection (e)(4) of Section 37 defines Data Center as a use involving a building or premise in which the primary use is occupied by computers and telecommunications and related equipment, including supporting equipment, where information is processed, transferred or stored. The definition sits in the EDID definitions and applies there.
Is there a parking requirement for a data center in the EDID?
The Table of Parking Requirements in Section 37 has no Data Center line. Its "All other uses" row says the requirement is to be determined by the Building Commissioner based on a similar use in the table, taking into account data the Applicant submits. Spaces must be at least 9 feet wide and at least 18 feet long.
Does this page apply to Everett, Washington?
No. This page covers only the City of Everett, Massachusetts, in Middlesex County, whose City Council adopts the Revised Ordinances read here. Everett, Washington is a separate city in Snohomish County with its own code and its own data center rules.

Sources & Official References

Other rules in Everett

All Everett rules

Compare Everett to another location·View the Massachusetts data centers & crypto mining overview

Get notified when Data Center Zoning & Siting in Everett, MA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.