Everett, MA Data Centers & Crypto Mining: Data Center Zoning & Siting (2026)
Key Facts
- District covered
- Everett Docklands Innovation District, Subdistricts A and B
- Data Center use table row
- Y, Y, SP, SP, SP, SP
- Special Permit Granting Authority
- Planning Board
- Non-master maximum height
- 65 ft; master plan projects 370 ft with FAA limit
- FAR, non-master uses
- 1.0, increased to 4.0 by special permit
- Rooftop equipment screens
- Excluded from height up to 40 feet, 10 feet from roof edge
- Section added
- 10-28-2024 by Ord. No. C0260-24
Summary
In the City of Everett, Massachusetts (Middlesex County), the Zoning Ordinance lists a Data Center as a use in the Everett Docklands Innovation District under Section 37. A project outside a Master Plan Special Permit needs a special permit from the Planning Board in Subdistrict A and Subdistrict B, at any size. Nothing in that table makes it a by-right use.
a) Master Plan Developments: ... "Y" indicates that the Planning Board may, in its discretion, permit a use as part of the Master Plan Special Permit. Any use of such land must be specifically identified and approved in such Master Plan Special Permit. ... b) Non-Master Plan Developments: "Y" indicates that the use is allowed by right in the district. ... USE CATEGORY Master Planned Uses Non-Master Planned Uses Less Than 5,000 sq ft of Gross Floor Area Non-Master Planned Uses Greater Than 5,000 sq ft of Gross Floor Area RESIDENTIAL Sub A Sub B Sub A Sub B Sub A Sub B ... INNOVATION ... Data Center Y Y SP SP SP SP ... Data Center: Data Center shall mean a use involving a building/premise in which the primary use is occupied by computers and/or telecommunications and related equipment, including supporting equipment, where information is processed, transferred and/or stored.
Full Breakdown
Section 37 of the Everett Zoning Ordinance, added on 10-28-2024 by Ord. No. C0260-24, governs the Everett Docklands Innovation District, the EDID. The district has 2 subdistricts, Subdistrict A and Subdistrict B. Under the INNOVATION heading of the use table, the row for Data Center reads Y, Y, SP, SP, SP, SP. The six columns are Master Planned Uses, Non-Master Planned Uses Less Than 5,000 sq ft of Gross Floor Area, and Non-Master Planned Uses Greater Than 5,000 sq ft of Gross Floor Area, each split into Sub A and Sub B.
The ordinance defines the term in subsection (e)(4): a use involving a building or premise in which the primary use is occupied by computers and telecommunications and related equipment, including supporting equipment, where information is processed, transferred or stored. For a Master Plan Development, Y means the Planning Board can, in its discretion, permit the use inside a Master Plan Special Permit, and the use must be specifically identified and approved there. For non-master-planned projects the mark is SP, and the Planning Board is the Special Permit Granting Authority. A Y for a non-master development would mean by right, but the Data Center row never carries one.
The EDID dimensional table gives non-master-planned uses a 10 ft. front yard, a 10 ft. side yard, a 20 ft. rear yard, a maximum height of 65 ft, and FAR of 1.0, which can be increased to 4.0 by special permit. Master Plan Special Permit projects list a maximum height of 370 ft, with a footnote tying that figure to the height that complies with FAA and Massport critical airspace limits. Rooftop screens, fully enclosed mechanical penthouses or fences erected to conceal equipment are excluded from the height calculation up to 40 feet, if set back a minimum of 10 feet from the roof edge. The parking table has no Data Center row, and its "All other uses" line leaves the figure to the Building Commissioner.
Violations & Fines
Section 37 prints no penalty clause of its own. A data center that is not identified in an approved Master Plan Special Permit, or approved by special permit from the Planning Board where the table shows SP, is not an allowed use in the district. The Building Commissioner classifies unlisted uses and notes the classification on the building permit.
Frequently Asked Questions
Where in Everett, Massachusetts can a data center be built?
How does the ordinance define a data center?
Is there a parking requirement for a data center in the EDID?
Does this page apply to Everett, Washington?
Sources & Official References
Other rules in Everett
Compare Everett to another location·View the Massachusetts data centers & crypto mining overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.
Data Center Zoning & Siting in Nearby Cities
How other cities in this county handle data center zoning & siting.