Key Facts

Permitted districts
Light (I), Medium (J), Heavy (K) Industrial only
Table designation
"P" = by right, no asterisk/supplemental standard
Excluded districts
All commercial, special-purpose, residential columns blank
Height cap in "I" district
3 stories or 55 feet
Parking in "I" district
1 space per 500 sq ft or 3 employees
Unlisted-use process
Written determination available under § 4.802

Summary

Fort Worth's zoning ordinance defines 'data center' as its own land use and permits it by right only in the city's three industrial districts: Light Industrial (I), Medium Industrial (J) and Heavy Industrial (K). Every commercial, special-purpose and residential district leaves the use blank, meaning it is not allowed there without a case-by-case determination.

DATA CENTER. Real and personal property consisting of buildings or structures specifically designed or modified to house networked computers and data and transaction processing equipment and related infrastructure support equipment, including, without limitation, power and cooling equipment, used primarily to provide, as a service to persons other than the company operating the data center, data and transaction processing services, outsource information technology services and computer equipment colocation services, or, used primarily to provide, to a single user, including the user's affiliates, customers, lessees, vendors and other persons authorized by the user, data and transaction processing services. ... (a) Permitted uses (P). A "P" in a cell indicates that a use is allowed by right in the respective zoning district. Permitted uses are subject to all other applicable regulations of this zoning ordinance.

Full Breakdown

101 defines DATA CENTER as real and personal property consisting of buildings or structures specifically designed or modified to house networked computers and data and transaction processing equipment, including power and cooling infrastructure, whether operated as a service to outside customers or for a single user's own affiliates and vendors. 803 lists 'Data center' with a plain 'P' (no asterisk) in only three of the table's thirteen zoning columns: I (Light Industrial), J (Medium Industrial) and K (Heavy Industrial). 801(d) states an empty cell means the use is not allowed in that district, though a conditional use permit can be sought under Chapter 4, Article 4 for any use not permitted anywhere.

Because 'Data center' carries no asterisk in the table, none of the Chapter 5 supplemental use standards apply, and no CUP or special exception review is required inside I, J or K. 1000(c)-(d) sets a 3-story/55-foot height cap, a 10-foot rear yard where adjacent to residential zoning, a 5-foot interior side yard where adjacent to residential zoning, off-street parking of one space per 500 square feet of gross floor area (or one per three employees, whichever is greater), and landscaping of 4% of net site area or a 30-foot buffer along public rights-of-way. 1004 for moderate- and heavy-intensity industrial uses respectively. No moratorium, crypto-mining-specific rule, or additional data-center overlay appears elsewhere in the zoning ordinance text.

Violations & Fines

Operating a data center outside the I, J or K districts without first obtaining a conditional use permit under Chapter 4, Article 4 is a zoning code violation, enforceable through Fort Worth Code Compliance the same as any unpermitted land use. A property owner unsure whether a proposed facility fits the definition can request a written determination from the zoning administrative official under § 4.802 before building rather than risk a stop-work order or denied certificate of occupancy.

Frequently Asked Questions

Can a data center be built in a Fort Worth commercial zone?
Not by right. The § 4.803 use table only marks 'Data center' with a 'P' in the I, J and K industrial columns; the commercial columns (ER, E, FR, F, G, H) are blank, which § 4.801(d) defines as not allowed. A conditional use permit could be sought under Chapter 4, Article 4, but the base table does not authorize it there.
Does Fort Worth require a special permit to open a data center in Light Industrial zoning?
No. The table entry for 'Data center' in the I, J and K columns is a plain 'P' with no asterisk, so under § 4.801(a) it is permitted by right, subject to the ordinance's general development standards, without a supplemental-use hearing, special exception, or conditional use permit.
What dimensional standards apply to a data center in Fort Worth's Light Industrial district?
Section 4.1000(c) caps building height at 3 stories or 55 feet, requires a 10-foot rear yard and 5-foot interior side yard only where the lot is adjacent to residentially zoned land, and sets no front yard requirement if the whole block frontage is zoned FR through K.
Is there a moratorium on new data centers in Fort Worth?
No moratorium or crypto-mining-specific provision appears in the zoning ordinance text; the only local rule found is the standard use-table restriction confining the defined 'data center' use to the Light, Medium and Heavy Industrial districts under § 4.803.

Sources & Official References

Other rules in Fort Worth

All Fort Worth rules

Texas rules heatmap·Compare Fort Worth to another location·View the Texas data centers & crypto mining overview

Get notified when Data Center Zoning & Siting in Fort Worth, TX changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.