Key Facts

Governing table
Table 89-21-2, Sec. 89-21
Permitted by right
MN, MX, D, CM, CH, PI-H, IL, IH
Accessory use only
PI-L (Public/Institutional-Light)
Not permitted
A, RS-1, RS-2, RM districts
Use category
Industrial/Production - Manufacturing & Employment
Remedy if blank
Apply for rezoning to a permitting district

Summary

Lafayette Consolidated Government's Unified Development Code gives data centers their own use classification, "Data Processing, Hosting, and Related Services (including data centers)," in the Sec. 89-21 Use Table. The table lets data centers locate by right in eight commercial, mixed-use and industrial districts, restricts them to an accessory role in Public/Institutional-Light, and bars them outright from Agricultural and every residential district.

P By right The use is permitted if it meets the standards established in the zoning district, and any other applicable standards of this Chapter. ... A Accessory Use A use customarily incidental and subordinate to the principal use or building and located on the same lot with the principal use or building. Not permitted A blank cell indicates that the use is not allowed in the district. A property owner who wants to establish the use may apply for a rezoning to a district that does allow the use. ... Data Processing, Hosting, and Related Services (including data centers) P P P P P A P P P

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 65).

Full Breakdown

Table 89-21-2 assigns every land use in the parish a "P" (permitted by right), "C" (conditional use permit from the applicable Zoning Commission), "A" (accessory only) or a blank cell (not allowed) in each of the code's thirteen zoning districts. For "Data Processing, Hosting, and Related Services (including data centers)," filed under the Industrial/Production - Manufacturing & Employment category, the row reads P in Mixed-Use Neighborhood (MN), Mixed-Use Center (MX), Downtown (D), Commercial Mixed (CM), Commercial Heavy (CH), Public/Institutional-Heavy (PI-H), Industrial Light (IL) and Industrial Heavy (IH); A in Public/Institutional-Light (PI-L); and blank in Agricultural (A), and both Residential Single-Family districts (RS-1, RS-2) and Residential Mixed (RM).

A blank cell is not a soft preference: Sec. " Because a data center still has to satisfy every other standard tied to whichever district it lands in - landscaping/buffer requirements of Sec. 89-36, parking ratios of Sec. 89-39, and any applicable overlay under Sec. 89-22 - the use-table entry is only the first gate, not the whole approval. If an operator proposes a format the table doesn't squarely describe, Sec. 89-21(c) lets the administrator classify it by NAICS code or by comparison to how similarly sized jurisdictions have zoned equivalent facilities.

Violations & Fines

Operating or constructing a data center use on a lot zoned Agricultural, RS-1, RS-2 or RM is not merely discouraged, it is an unlisted, disallowed use under Sec. 89-21(b); the code's own remedy is that "a property owner who wants to establish the use may apply for a rezoning to a district that does allow the use" rather than seeking a variance or waiver.

Frequently Asked Questions

Can a data center be built in a Lafayette residential zone?
No. The Sec. 89-21 Use Table leaves the cell blank for RS-1, RS-2, RM and Agricultural districts, and Sec. 89-21(b) defines a blank cell as meaning the use is not allowed there; the property would need to be rezoned to a district that lists the use before the project could move forward.
Which Lafayette zoning districts allow data centers by right?
Mixed-Use Neighborhood, Mixed-Use Center, Downtown, Commercial Mixed, Commercial Heavy, Public/Institutional-Heavy, Industrial Light and Industrial Heavy all show a "P" for Data Processing, Hosting, and Related Services, meaning the use is permitted if it meets the district's other standards.
Can a small server room be added to a PI-L building?
Only as an accessory use. The Use Table marks Public/Institutional-Light with an "A" for this category, so a data-processing function has to be secondary to the site's principal permitted use rather than the primary business on the lot.
What if my proposed facility doesn't match this use definition exactly?
Sec. 89-21(c) allows the administrator to approve an undefined use if it functions like a listed one, shares similar visual, traffic or environmental impacts, falls in the same NAICS classification, or is one that comparable jurisdictions have already zoned successfully.

Sources & Official References

Other rules in Lafayette

All Lafayette rules

Compare Lafayette to another location·View the Louisiana data centers & crypto mining overview

Get notified when Data Center Zoning & Siting in Lafayette, LA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.