Paulding County, GA Data Centers & Crypto Mining: Data Center Zoning & Siting (2026)
Key Facts
- Overlay size
- ~995 acres, 12 tax parcels
- Minimum lot
- 50 acres
- Max building coverage
- 50% of lot
- Max height
- 75 feet
- Minimum setbacks
- 75 ft front/side/rear
- Parking
- 3 spaces per 1,000 sq ft office space
Summary
Paulding County only allows large-scale data centers inside its Technology Park Overlay District, a fixed set of tax parcels totaling roughly 995 acres. Section 220-40.01 sets the district's purpose, while Sections 220-40.04 and 220-40.05 fix a 50-acre minimum lot, a 50 percent building-coverage cap and a 75-foot height limit for qualifying developments.
220-40.01 Purpose and Intent. The purpose and intent of the Technology Park Overlay District that allows the siting of "Data Centers" in designated areas of 50 acres or greater in size, which Data Centers may include computers and data center equipment, data storage and hosting technologies, and other new technologies, under certain conditions set by the County. The conditions of this Technology Park Overlay District are established to ensure the availability of adequate water and electrical utility resources, set-backs, buffer areas, noise levels and noise attenuation methods, screening, security, and protection of adjacent and nearby uses from adverse impacts. ... 220-40.04 Lot Size, Area and Setback Requirements. A.Minimum Lot Acreage: 50 acresB.Building Coverage Limit: 50% maximum total building coverage as a percent of total lot area ... 220-40.05 Height Regulations. Buildings shall not exceed a height of 75 feet, measured from structure pad level.
Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 35).
Full Breakdown
01, 'to allow the siting of Data Centers in designated areas of 50 acres or greater in size,' covering computers, data storage and hosting technology under conditions meant to secure adequate water and electrical utility capacity, setbacks, buffers, noise attenuation and screening. 02 fixes the overlay to twelve specific tax parcels totaling roughly 995 acres, and the Board of Commissioners may only redraw that boundary through the Chapter 280 rezoning procedure. 03 permits uses such as computing infrastructure, data processing, web hosting, custom computer programming and public utilities alongside accessory power and cooling equipment.
06), and caps building coverage at 50 percent of the lot. 05 limits building height to 75 feet measured from the pad, though the Community Development Director can approve taller incidental elements such as water towers or HVAC equipment on a showing of technical necessity. 08 if built to county road standards.
Violations & Fines
Locating a data center outside the mapped ~995-acre overlay, undercutting the 50-acre minimum lot or 75-foot setbacks, or exceeding the 75-foot height cap without the Community Development Director's sign-off is a Title 2 zoning violation the Zoning Administrator can cite. Boundary expansion requires a formal Chapter 280 rezoning, not administrative approval, and an administrative enforcement decision may be appealed to the Zoning Board of Appeals within 30 days under Section 290-40.01.
Frequently Asked Questions
Can a data center be built anywhere in Paulding County?
How big does the lot have to be?
How tall can a data center building be?
Sources & Official References
Other rules in Paulding County
Compare Paulding County to another location·View the Georgia data centers & crypto mining overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.