Texas City, TX Data Centers & Crypto Mining: Data Center Zoning & Siting (2026)

Significant Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Data centers named in
§ 162.02, definition of SIMILAR PROJECTS
Who decides applicability
Director of Engineering and Planning, at application
Zoning district
District S-P, Site Plan, under § 160.051
Application fee
$5,000, in addition to other permit fees
BESS site spacing
1,500 feet from another BESS site
Single-family or school setback
At least 200 feet for a perimeter fence

Summary

Chapter 162 of the Texas City Code of Ordinances, written for battery energy storage systems, defines similar projects to include data centers and similar high energy demand installations, with applicability decided by the Director of Engineering and Planning at application. Covered uses are restricted to District S-P, Site Plan, with a $5,000 application fee.

SIMILAR PROJECTS. ... Data centers and similar high energy demand installations which may or may not return energy to the grid. Applicability of this chapter shall be determined by the Director of Engineering and Planning at the time of application. ... (A) BESS facilities and similar uses shall be restricted to locations zoned in accordance with Chapter 160 - "Zoning," § 160.051, District S-P - Site Plan. ... (B) A BESS site shall be no closer than 1,500 feet perpendicular in any direction from another BESS site measured at the perimeter fence. This distance may be increased or reduced by the City Commission upon recommendation from the Planning Board and Zoning Commission.

Full Breakdown

Ord. 2025-06, passed August 6, 2025, created Chapter 162 to regulate Battery Energy Storage System (BESS) and similar project sites. Section 162.02 defines SIMILAR PROJECTS as data centers and similar high energy demand installations which may or may not return energy to the grid, and provides that applicability of the chapter is determined by the Director of Engineering and Planning at the time of application. Data centers are named nowhere else in the code as exported, and crypto mining is not named at all, so this chapter is the only place a data center is addressed.

Section 162.03(A) restricts BESS facilities and similar uses to locations zoned District S-P, Site Plan, under Section 160.051. Section 160.051(C)(1)(b)14 adds that the basic district most closely comparable to these projects is District F, Light Industrial, but that site-specific review under District S-P is required in all districts, including District F. The Planning Board and Zoning Commission and the City Commission each have broad discretion over the development and its intended use and operation. Section 162.03(B) requires installations to be unmanned and prohibits on-site office or shop facilities, while allowing equipment storage and maintenance facilities that are not permanently attended.

Section 162.04 requires a Development Plan filed with the Engineering and Planning Department with a $5,000 application fee, in addition to fees for zoning change, platting, building permits or certificates of occupancy. The plan must include a site plan showing distances to adjacent property lines and structures, a landscaping and screening plan, elevations and renderings, and a reimbursement agreement for the city's third party expert.

Section 162.05 sets location standards written for BESS sites: BESS sites no closer than 1,500 feet to another BESS site, a perimeter fence setback of at least 200 feet from the nearest property zoned for single-family uses or a school, and no installation in a FEMA designated Special Flood Hazard Area. Because the chapter's spacing and setback text speaks of BESS sites, the Director's applicability decision determines how these numbers apply to a data center proposal.

Violations & Fines

Chapter 162 prints no penalty section of its own. Its stated consequences run through permitting and occupancy: a deferral of platting requirements under Section 162.05(K), or of landscaping under Section 162.07(F), that is not satisfied in an acceptable timeframe can result in revocation or non-renewal of the Certificate of Occupancy for the site. Section 162.21 requires 30 days written notice to the Engineering and Planning Department before a change in ownership, and the applicant remains liable for the approved Development Plan conditions.

Frequently Asked Questions

Does Texas City regulate data centers by name?
Once, in Section 162.02. It defines SIMILAR PROJECTS as data centers and similar high energy demand installations which may or may not return energy to the grid. The chapter otherwise addresses battery energy storage systems, and the definition provides that applicability is determined by the Director of Engineering and Planning at the time of application.
What zoning district does a data center need in Texas City?
Section 162.03(A) restricts BESS facilities and similar uses to locations zoned District S-P, Site Plan, under Section 160.051 of the zoning chapter. Section 160.051 adds that S-P site-specific review is required in all districts, including District F, Light Industrial, and gives the Planning Board, Zoning Commission and City Commission broad discretion.
What does the application cost?
Section 162.04(A) sets a $5,000 fee due at submittal of the Development Plan, in addition to any other fees for zoning change, platting, building permits or certificates of occupancy. Section 162.04(B) directs the application to the Engineering and Planning Department, and Section 162.04 includes a reimbursement agreement for the city's third party expert.
Are there distance requirements from homes or schools?
Section 162.05(C) sets the perimeter fence setback for a BESS site at the greater of 200 feet from the nearest property zoned for single-family uses or a school, a distance required by plume modeling and testing data, or a distance set by the City Commission. Whether that applies to a data center depends on the Director's determination under Section 162.02.
Is there a data center moratorium in Texas City?
The Texas City Code of Ordinances as exported on September 8, 2026 prints no data center moratorium in the text searched. The governing provisions found are Section 162.02, Section 162.03 and Section 160.051, which route covered projects through District S-P site plan review with City Commission discretion.

Sources & Official References

Other rules in Texas City

All Texas City rules

Texas rules heatmap·Compare Texas City to another location·View the Texas data centers & crypto mining overview

Get notified when Data Center Zoning & Siting in Texas City, TX changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.