Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Dedicated Ordinance
None; industrial zoning
Allowed Zones
M-1 Light, M-2 General Industrial
Data Center Status
Unlisted; classified as industrial use
Environmental Review
CEQA if discretionary
Site Coverage
Max 75% of site

Summary

Tehama County has no dedicated data-center ordinance. In the unincorporated county a server facility is an industrial use, allowed in the M-1 Light Industrial and M-2 General Industrial zones under Title 17, subject to a use permit and CEQA review. Red Bluff and Corning set their own zoning.

These county ordinances apply to unincorporated areas of Tehama County. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

Examples of uses include light to heavy manufacturing, fabrication, storage and warehousing, processing of goods and resources, energy facilities, equipment sales and storage yards, business and office parks and other such uses which because of their operations, may create noise, light or glare, dust or odor which are not compatible with residential or service and retail commercial uses.

Source: Tehama County Zoning Code (Title 17) and General Plan (2009-2029)View official code

Official source re-checked September 7, 2026: the cited page had not changed since it was quoted.

Full Breakdown

Rural Tehama County does not name data centers in its zoning code (Title 17). Its only industrial designation, General Industrial, is carried out through the M-1 Light Industrial and M-2 General Industrial districts, which permit manufacturing, warehousing, energy facilities, and business or office parks. Because a data center is unlisted, the Planning Department classifies it as a similar industrial use, allowed by right in M-1 or M-2 or, for larger power-intensive campuses, through a use permit heard by the Planning Commission. Discretionary approvals trigger CEQA and a General Plan acoustical analysis. General Industrial development may not cover more than 75% of the site and must buffer adjacent homes. These rules govern unincorporated land only.

Violations & Fines

Building a data center on land not zoned M-1 or M-2, or without a required use permit or CEQA clearance, is a zoning violation. The county can withhold building permits and issue stop-work orders until the parcel conforms.

Frequently Asked Questions

Where can a data center be built in unincorporated Tehama County?
In the M-1 Light Industrial or M-2 General Industrial zones. With no data-center-specific rule, the Planning Department classifies a server facility as an industrial use, permitted by right or by use permit, with CEQA review for larger projects.
Does Tehama County have data center rules, and how can I weigh in?
No, Tehama County has no dedicated data-center ordinance; server facilities are handled through M-1/M-2 industrial zoning, General Plan noise standards, and CEQA. To advocate for one, contact the Board of Supervisors at https://www.tehama.gov/board-of-supervisors/.
Do these county rules apply inside Red Bluff or Corning?
No. Title 17 governs only unincorporated Tehama County. The incorporated cities of Red Bluff and Corning adopt and enforce their own zoning codes within their city limits.

Sources & Official References

Other rules in Tehama County

All Tehama County rules

California rules heatmap·Compare Tehama County to another location·View the California data centers & crypto mining overview

Get notified when Data Center Zoning & Siting in Tehama County, CA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.