Key Facts

MS4 impervious threshold
2,500 sq ft
General disturbance threshold
Over 1 acre
Permitting agency
Community Development & Services Agency
Governing code
§ 11.23.020(a)

Summary

Unincorporated Yuba County requires a grading permit for any disturbance over one acre, or 2,500-plus square feet of new impervious surface in MS4 areas.

These county ordinances apply to unincorporated areas of Yuba County. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

Any grading performed in the County of Yuba—Phase II Municipal Separate Sewer System (MS4) permit boundaries that creates or replaces 2,500 square feet or more of impervious surface shall require either a grading permit or a building permit. For these activities, the requirements within Code Section 7.50 shall apply.(2)For all projects excluding those covered in Subsection 11.23.020(a)(1) above, and except for the specific exemptions listed in Subsection 11.23.020(b), Grading Permit; Exemptions, no person shall do or permit to be done any grading on any site in the unincorporated areas of Yuba County without a valid grading permit obtained from the Community Development and Services Agency. A permit shall also be required for the following:a.Retaining walls which are over four feet in height, as measured from bottom of footing to top of the wall;b.Any retaining walls that are subject to surcharge;c.Private vehicular bridges;d.Fill operations exceeding four feet when filling an abandoned swimming pool unless a demolition permit for same is obtained from the Building Department.(3)A grading permit is required for any grading and/or other construction activity with ground disturbance of more than one acre, or any grading and/or construction activity smaller than one acre but part of a greater plan involving over one acre.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 6).

Full Breakdown

Yuba County Code § 11.23.020(a) requires a grading or building permit for any grading in Phase II MS4 boundaries that creates or replaces 2,500 square feet or more of impervious surface. Elsewhere in the unincorporated county, a grading permit is required for ground disturbance exceeding one acre, or any smaller project that's part of a larger plan totaling more than one acre. The Community Development and Services Agency issues the permit; a list of narrow exemptions covers minor cuts and fills under two feet deep.

Violations & Fines

Grading over the one-acre or 2,500-square-foot MS4 threshold without a permit is a Chapter 11.23 violation; the County can issue a stop-work notice and require the work be brought under permit.

Frequently Asked Questions

When does Yuba County require a grading permit?
When ground disturbance exceeds one acre, or when a project in MS4 boundaries creates or replaces 2,500+ square feet of impervious surface, § 11.23.020(a).
Are small grading jobs exempt from a permit?
Some are: cuts or fills under two feet deep, under 50 cubic yards, that meet several other conditions in § 11.23.020(b) can skip the permit.

Sources & Official References

Other rules in Yuba County

All Yuba County rules

California rules heatmap·Compare Yuba County to another location·View the California environmental rules overview

Get notified when Erosion Control in Yuba County, CA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.