Bozeman, MT Environmental Rules: Erosion Control (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Inspection interval
At least every 14 calendar days
After major storms
Inspect within 24 hours
Device removal
Only at 70 percent or greater permanent ground cover
Permit threshold
Disturbance of one acre or greater needs a director's permit
Required filings
NOI, SWPPP and NOT under § 40.04.350
Enforcement
Stop work order and city cleanup at owner's expense

Summary

In the City of Bozeman, Montana, owners and operators of construction sites must stabilize disturbed soil and stockpiles, install sediment controls, and inspect all BMPs at least every 14 calendar days and within 24 hours after major storms. Temporary erosion devices come off only at 70 percent permanent ground cover.

A.Erosion control. Owner/operator shall:1.Stabilize disturbed soil using recommended methods described in the city's Stormwater Master Plan;2.Stabilize or cover soil stockpiles to prevent sediment runoff or blowing of dust or sediment from the site;3.Prevent upland runoff that may erode disturbed slopes.B.Sediment control. Owner/operator shall:1.Provide sediment controls in the form of settling basins or traps, temporary seeding, perimeter controls or other BMP described in the city's Stormwater Master Plan; ... D.Removal of temporary erosion control devices. Owner/operator shall remove all temporary erosion control devices upon establishing 70 percent or greater permanent ground cover on a lot. ... 2.The permittee or the permittee's agent will be required to perform regularly scheduled site inspections, at least every 14 calendar days, and within 24 hours after major storm events to ensure all BMPs have been constructed and are functioning properly.

Full Breakdown

Bozeman Municipal Code § 40.04.360 sets the erosion and sediment rules for construction. The owner or operator must stabilize disturbed soil using the methods in the city's Stormwater Master Plan, stabilize or cover soil stockpiles to prevent sediment runoff or blowing dust, and prevent upland runoff that could erode disturbed slopes. Sediment controls take the form of settling basins or traps, temporary seeding, perimeter controls or other BMPs from the master plan, with settling basins designed where possible to adapt to long-term stormwater management. Adjacent properties are protected by a vegetative buffer, silt fence, fiber rolls or another appropriate BMP.

Site access and housekeeping are covered. The operator limits the number of temporary access entrances and uses BMPs so sediment is not tracked onto public streets or alleys by construction vehicles or washed into storm drains. Construction waste such as discarded building materials, concrete truck washout water, chemicals, litter and sanitary waste must be controlled, and failure to maintain good housekeeping practices is itself a violation of the article. Temporary erosion control devices are removed only after 70 percent or greater permanent ground cover is established on a lot.

Inspections are built in. The permittee or the permittee's agent performs scheduled site inspections at least every 14 calendar days and within 24 hours after major storm events, documents each inspection in writing, and makes the records available to the city. An authorized enforcement agent sets the frequency of city inspections of active sites.

Under § 40.04.350 the permit comes first. Disturbing one acre or greater requires a permit from the director before construction starts or a building permit issues, with an executed copy of the state's NOI, a SWPPP and, at completion, a NOT. Sites under one acre for multi-household, commercial, industrial or single-household construction also submit permit materials, and § 40.04.370 confirms the article applies to sites under one acre. The city can charge a permit fee under a resolution schedule, and the owner keeps the NOI, the state's confirmation letter and the SWPPP at the project site.

Violations & Fines

The city's enforcement agent and an official of the city's building division can issue a stop work order under § 40.04.350.H. If an owner fails to take corrective action on a spill or a release of pollutants, including sediment, the city can do the work or hire contractors and the owner reimburses every expense. By applying for a permit the owner consents to a lien for unpaid abatement costs and to withholding of a certificate of occupancy.

Frequently Asked Questions

How often must a Bozeman construction site inspect its erosion controls?
Section 40.04.360.G.2 requires the permittee or the permittee's agent to inspect at least every 14 calendar days and within 24 hours after major storm events. The inspections check that all BMPs have been constructed and are functioning properly, must be documented in writing, and the records must be made available for city review.
When can I remove silt fence and other temporary controls in Bozeman?
Under § 40.04.360.D, the owner or operator removes all temporary erosion control devices upon establishing 70 percent or greater permanent ground cover on a lot. Removing them earlier leaves the site out of step with the sediment control duties, and § 40.04.500 also lets the director require the removal of temporary BMPs.
Do small residential lots in Bozeman need erosion control?
Yes. Section 40.04.350.J.3 requires permit application materials for construction of single-household structures on sites under one acre, and § 40.04.370 applies the article to all sites under one acre. Section 40.04.380 also requires individual lots in a master plan development, regardless of size, to follow good housekeeping practices and the BMPs in the development's SWPPP.
What if mud gets tracked onto a Bozeman street from my site?
Section 40.04.360.C requires BMPs to ensure sediment is not tracked onto public streets or alleys by construction vehicles or washed into storm drains, and limits the number of temporary access entrances. If the owner does not correct a release of sediment, the city can perform the corrective work itself and the owner must reimburse the city for all expenditures.

Sources & Official References

Other rules in Bozeman

All Bozeman rules

Compare Bozeman to another location·View the Montana environmental rules overview

Get notified when Erosion Control in Bozeman, MT changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.