St. Tammany Parish, LA Environmental Rules: Erosion Control (2026)
Key Facts
- BMP duty
- Every construction site operator
- Stabilization
- Within 14 days of work stoppage
- SWPPP + NOI
- Required at 5+ acres
- SWPPP only
- Required 1 to under 5 acres
- Site plan
- Required with permit application
- Enforcement
- Occupancy certificate can be held
- Fees
- Set by Code § 2-009.00
Summary
St. Tammany Parish requires every construction site in the unincorporated parish, from single-family lots to subdivisions, to install and maintain Best Management Practices controlling silt, sediment, mud and clay discharge under its MS4 stormwater ordinance. Projects need an approved Stormwater Agreement and Construction Stormwater Site Plan before a building, site work or subdivision permit issues, plus an LDEQ SWPPP for sites disturbing an acre or more.
F.Stormwater Discharges from Construction Activities.1.No construction activity nor development shall degrade water quality in the receiving stream or adversely affect the MS4.2.All construction projects involving site work of any kind, including but not limited to subdivision development, minor subdivision development, residential construction, commercial construction, and roadway construction shall comply with the stormwater pollution prevention requirements of this section.3.All appropriate parish permits shall be obtained before the commencement of construction.4.All operators of construction sites shall use appropriate Best Management Practices or BMPs to control discharge to waterways and conveyances of the parish. Pollutants such as silt, sediment, mud, clay, and other construction contaminant materials associated with site work of any kind shall be controlled to the maximum extent practicable.
Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 12 Update 2).
Full Breakdown
Sec. 900-6.9(F) of the Unified Development Code makes every operator of a construction site, whether working on new residential or commercial construction, subdivision development, pool installation, pond excavation or a remodel that alters site drainage, responsible for controlling discharge to the parish's MS4, drainage infrastructure and waterways. Operators must use Best Management Practices selected from the Best Management Practices for Coastal Louisiana Nonpoint Source Pollution Handbook to keep silt, sediment, mud and clay off-site to the maximum extent practicable, and parish permits must be secured before construction starts.
An approved Stormwater Agreement, provided by the parish and signed at building-permit or site-work-permit stage, commits the owner to obtain any required LDEQ permit; subdivisions developed in phases file one at each phase's concept-plan stage. A Construction Stormwater Site Plan covering erosion control, sediment control and receiving-water impacts must accompany the permit application under Sec. 900-6.9(H). During construction, disturbed soil not actively worked must be stabilized within 14 days, BMPs must be self-inspected and repaired before the next storm, and a stabilized construction entrance/exit pad is required to keep mud off public roads. Sites of 5 acres or more (including phases of a larger common plan) need an LDEQ Notice of Intent and full SWPPP; sites between 1 and 5 acres need a SWPPP without an NOI. Capital projects run by parish personnel, life-safety emergency work, grave excavation and ordinary agricultural practices are exempt from the Stormwater Agreement and site-plan requirement, though the owner still must maintain erosion controls.
Violations & Fines
Parish stormwater inspectors check sites at the preliminary drainage inspection, at final inspection, and on an unscheduled basis; failure to correct problems after a failed inspection can trigger enforcement action under Sec. 900-6.9(J). The parish may withhold a certificate of occupancy until the final stormwater inspection confirms required controls are in place, and inspection and re-inspection fees are billed under Code of Ordinances § 2-009.00.
Frequently Asked Questions
Does a single-family home in St. Tammany Parish need an erosion control plan?
When does a St. Tammany Parish project need a full SWPPP and NOI?
How quickly must a construction site stabilize bare soil?
What can the parish do if BMPs fail during a storm?
Sources & Official References
Other rules in St. Tammany Parish
Compare St. Tammany Parish to another location·View the Louisiana environmental rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.