Key Facts

Trigger threshold
1 acre or more of land disturbance
Federal reference
40 CFR 122.26(b)(14)(i)-(x)
Applies to
Clearing, grading, excavation activity
Civil penalty
Up to $1,000/day per violation
Criminal penalty
Up to $1,000 fine and/or 6 months jail
Enforcing agency
Director, Dept. of Public Works

Summary

Baton Rouge/EBRP Code Sec. 2:363(e) puts any construction project that disturbs one acre or more of land, city-parish-wide, under the stormwater chapter's erosion and sediment control rules and EPA/DEQ construction-activity regulations. Builders must be ready to hand the Director of Public Works a copy of their EPA or DEQ construction discharge permit on request.

These county ordinances apply to unincorporated areas of East Baton Rouge Parish. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

Any construction operation that results in the disturbance of one (1) acre or more of total land area is subject to the regulations of this chapter and EPA and DEQ regulations ... These regulations specifically apply to clearing, grading, and excavation activities. Not subject to regulation are disturbances of less than one (1) acre, unless the smaller parcel creates a significant stormwater quality or MSSS problem.

Full Breakdown

Sec. 26(b)(14)(i)-(x), describing operations that use heavy equipment such as bulldozers, cranes and dump trucks, clear trees and rockwork, and install haul roads, drainage systems and holding ponds. The ordinance adopts the EPA's own finding that construction runoff 'has the potential for serious water quality impacts,' particularly from sediment. These regulations specifically apply to clearing, grading, and excavation activities, and disturbances of less than one acre are not subject to regulation unless the smaller parcel creates a significant stormwater quality problem, per the same subsection.

Sec. 2:363(f) additionally requires that potential discharge areas, including parking lots, subdivision developments and construction sites, comply with all standards set by the city-parish's planning and zoning office and the Department of Public Works' engineering, inspection and environmental divisions. Sec. 2:362(a)(9) reinforces that erosion-control ordinances are never exempted from Chapter 8, and a failure to comply with erosion-control requirements is enforced through this chapter's remedies. Contractors must supply a copy of their construction activity general discharge permit to the Director of Public Works upon request under Sec.

2:363(e), and dischargers more broadly must provide a stormwater management plan on request under Sec. 2:363(b)-(c) showing use of the best available sediment control technology.

Violations & Fines

A violation of the one-acre erosion-control trigger is enforced the same as any other stormwater violation under Sec. 2:369: a civil penalty of up to $1,000.00 per day, per violation, plus the City-Parish's attorney's fees and litigation costs (Sec. 2:369(c)). A contractor who discharges sediment-laden runoff without first securing the required EPA or DEQ construction permit commits a criminal violation under Sec. 2:369(d)(3), punishable upon conviction by a fine of up to $1,000.00, imprisonment of up to six months, or both. The Director of Public Works may also seek a court injunction to halt an active violation under Sec. 2:369(b).

Frequently Asked Questions

At what project size does East Baton Rouge Parish require erosion control?
Sec. 2:363(e) sets the trigger at disturbance of one acre or more of total land area, which brings the project under Chapter 8's stormwater rules plus EPA and DEQ construction regulations. A smaller parcel can still be regulated if it creates a significant stormwater quality problem.
Do I need a permit before starting grading on a construction site?
Yes. Sec. 2:363(e) requires the contractor to provide the Director of Public Works a copy of the construction activity discharge permit issued by EPA or DEQ on request, and Sec. 2:363(f) requires compliance with planning and zoning and Department of Public Works engineering, inspection and environmental standards.
What is the penalty for erosion-control violations on a job site in the parish?
Enforcement runs through Sec. 2:369: a civil penalty of up to $1,000 per day per violation, plus the parish's attorney's fees, and a possible criminal charge with a fine up to $1,000 and up to six months in jail for discharging without the required construction permit.

Sources & Official References

Other rules in East Baton Rouge Parish

All East Baton Rouge Parish rules

Compare East Baton Rouge Parish to another location·View the Louisiana environmental rules overview

Get notified when Erosion Control in East Baton Rouge Parish, LA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Erosion Control in Cities Across East Baton Rouge Parish