St. Louis County, MO Environmental Rules: Erosion Control (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Idle-soil trigger
14 days without activity
Stabilization deadline
7 days once triggered
Settling basin threshold
10+ disturbed acres
Max cut/fill slope
3:1
Enforcing agency
Dept. of Transportation & Public Works

Summary

St. Louis County's Land Disturbance Code sets hard deadlines for stabilizing bare soil on active construction sites, plus sediment-trapping design standards.

City-specific rules exist: Florissant has its own erosion control rules that differ from St. Louis County's county-level regulations. If you live in Florissant, check the city-specific page instead.

Permit holder shall install temporary stabilization when soil disturbing activities will cease on any portion of the site and are not planned to resume for a period exceeding fourteen (14) calendar days. Temporary stabilization must be initiated immediately upon knowing the duration is more than fourteen (14) days. Temporary stabilization must be completed within seven (7) calendar days.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 85 | Traffic: Supplement 80).

Full Breakdown

Any construction or land disturbance site in unincorporated St. Louis County must control erosion under the county's Land Disturbance Code (Chapter 1114). Bare soil that will sit idle more than 14 days needs temporary stabilization started immediately and finished within 7 days; once grading permanently stops, final stabilization must start immediately and finish within 7 days too. Sites over 10 disturbed acres need settling basins sized for a two-year, 24-hour storm, and cut/fill slopes are capped at 3:1. The Department of Transportation and Public Works enforces this through the land disturbance permit and required weekly/after-rain inspections by a qualified special inspector.

Violations & Fines

Unpermitted land disturbance or failing to correct a cited violation within 7 days of written notice is unlawful; the County Counselor can pursue a court action to restrain, correct, or abate the violation.

Frequently Asked Questions

When does a construction site have to stabilize bare soil?
Once soil-disturbing work stops on any part of the site for more than 14 days, temporary stabilization must start right away and be finished within 7 calendar days.
Does this apply inside incorporated cities in the county?
It applies in unincorporated St. Louis County and in any municipality that has contracted with the County to enforce the Land Disturbance Code.

Sources & Official References

Other rules in St. Louis County

All St. Louis County rules

Compare St. Louis County to another location·View the Missouri environmental rules overview

Get notified when Erosion Control in St. Louis County, MO changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Erosion Control in Cities Across St. Louis County