Stabilization deadline
7 calendar days after disturbance ends
1-5 acre disturbance
Sediment trap required
Over 5 acres
Sediment basin with filtered riser
Inspector required
Over 10 acres of disturbance
Applies to
Unincorporated Lake County only

Summary

Unincorporated Lake County requires soil erosion and sediment control measures on any regulated land disturbance, with specific stabilization timelines and sediment-trapping standards by disturbed acreage.

These county ordinances apply to unincorporated areas of Lake County. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

Soil erosion and sediment control related measures are required to be constructed and maintained for any regulated land disturbance activity, in accordance with the standards of this section. All temporary measures and permanent erosion and sediment control shall be maintained continuously in an effective, working condition. ... Disturbed areas shall be stabilized with temporary or permanent measures within seven calendar days following the end of active hydrologic disturbance, or redisturbance...

Source: Lake County Watershed Development OrdinanceView official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: 2026 S-15: Supplement contains: Local legislation current through Ord. 26-0618, passed 6-9-2026 | State legislation current through ILCS Pamphlet 2025 #5).

Full Breakdown

Lake County Code § 151.146(J) requires erosion and sediment control measures for any regulated land disturbance activity in unincorporated Lake County, maintained continuously in effective working condition. Disturbed areas must be stabilized with temporary or permanent measures within 7 calendar days after active disturbance ends. Control requirements scale with tributary area: sites disturbing 1,000 sq ft to 1 acre need a filter barrier or equivalent; 1 to 5 acres need a sediment trap; over 5 acres need a sediment basin with filtered riser pipe. Projects over 10 acres (or smaller with floodplain/waters exposure) must retain a Designated Erosion Control Inspector who logs conditions and reports noncompliance to the Planning, Building and Development Director within 24 hours. This chapter (the Unified Development Ordinance) applies only to unincorporated county land per § 151.003. Waukegan, North Chicago, Highland Park, Gurnee, Libertyville, Mundelein and other municipalities enforce their own separate erosion control rules.

Violations & Fines

Enforced by the Planning, Building and Development Director; noncompliant sites can be denied site development permits or certificates of occupancy, and required temporary controls must be removed within 30 days of final stabilization or as no longer needed.

Frequently Asked Questions

Does this rule apply inside Waukegan or Highland Park?
No. Chapter 151 applies only to unincorporated Lake County; incorporated cities and villages enforce their own separate erosion and stormwater ordinances.
How fast must a construction site be stabilized after grading stops?
Within 7 calendar days of the end of active hydrologic disturbance, using seeding, mulching, sodding, or an approved non-vegetative measure.

Sources & Official References

Other rules in Lake County

All Lake County rules

Compare Lake County to another location·View the Illinois environmental rules overview

Get notified when Erosion Control in Lake County, IL changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Erosion Control in Cities Across Lake County