Independence, MO Environmental Rules: Erosion Control (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Governing law
Independence City Code Ch. 17, Art. 13
Trigger threshold
Over 1,000 sq ft of disturbance
Bond amount
$1,000/acre, capped at $10,000
Bond hold period
2 years after installation
Permit authority
Municipal Services Director

Summary

Independence requires an erosion control permit, plan, and financial bond for clearing, grubbing, grading, or building construction that disturbs more than 1,000 square feet.

An erosion control permit is required for all clearing, grubbing, grading and building construction projects, except where land disruption is 1,000 square feet or less. An application for an erosion control permit shall be made to the Public Works [Municipal Services] Director on forms furnished. The application must be accompanied by an erosion control plan prepared in accordance with applicable provisions contained herein.

(Ord. No. 19502, § 1, 11-6-2023)

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 13).

Full Breakdown

Independence City Code § 17.13.002 requires an erosion control permit for all clearing, grubbing, grading and building construction projects, except where land disturbance is 1,000 square feet or less; applicants file an erosion control plan with the Municipal Services Director. Under § 17.13.003, the owner must post a performance and maintenance bond of $1,000 per disturbed acre (capped at $10,000) before the permit issues or work begins, released two years after the erosion control measures are installed. Section 17.13.004 bars any clearing, grubbing, grading, or construction from starting without the permit and its fee.

Violations & Fines

Fines of $100–$500 per violation under § 17.13.005, with each day a separate offense, plus forfeiture of the performance/maintenance bond for uncorrected erosion damage.

Frequently Asked Questions

Do I need a permit to clear a small lot in Independence?
Only if disturbance exceeds 1,000 square feet. City Code § 17.13.002 exempts smaller clearing, grubbing, or grading jobs from the erosion control permit requirement.
What bond does Independence require for erosion control work?
A performance and maintenance bond of $1,000 per disturbed acre, capped at $10,000, held for two years from installation of the erosion control measures, per § 17.13.003.

Sources & Official References

Other rules in Independence

All Independence rules

Compare Independence to another location·View the Missouri environmental rules overview

Get notified when Erosion Control in Independence, MO changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Erosion Control in Nearby Cities

How other cities in Jackson County handle erosion control.

Kansas City, MO
Some Restrictions