Lakewood, CO Environmental Rules: Erosion Control (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Permit issuer
Planning & Public Works Directors
Plan validity
6 months from approval
Small-fill exemption
Under 1 ft, on flat terrain
Small-cut exemption
Under 2 ft, gentle slope

Summary

Lakewood requires a grading permit from the Planning and Public Works Directors before any excavation, fill, or earthwork on private property, with narrow exemptions for small cuts, fills, and utility trenching.

No person shall do any grading without first having obtained a grading permit from the Planning Director, and Public Works Director except for the following:1.An excavation below finished grade for basements and footings of a building, retaining wall or other structure authorized by a valid building permit... 7.An excavation which is (a) less than two feet in depth, or (b) which does not create a cut slope greater than two feet in height and steeper than three horizontal to one vertical.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Municipal Code: Supplement 14 | Zoning Ordinance: ?).

Full Breakdown

Chapter 14.21 of the Lakewood Municipal Code requires anyone doing grading, cuts, fills, or earthwork construction, to first obtain a grading permit from the Planning Director and Public Works Director. Limited exemptions apply, including shallow excavations authorized under a valid building permit, small cuts under two feet with a slope no steeper than three-to-one, minor fills under one foot on flat terrain, and well or utility excavations. A grading plan must be accompanied by a final site plan and is valid for six months from approval. The Director can require an approved haul route and dump site for excess material.

Violations & Fines

Grading without a required permit can trigger a stop-work order, denial of a certificate of occupancy for the project, and other enforcement action the Director deems necessary.

Frequently Asked Questions

Do I need a permit to grade my Lakewood property?
Yes: a grading permit from the Planning Director and Public Works Director is required unless a narrow exemption applies, such as a small cut under two feet.
How long is a Lakewood grading permit good for?
The approved grading plan is valid for six months from the date of approval.

Sources & Official References

Other rules in Lakewood

All Lakewood rules

Compare Lakewood to another location·View the Colorado environmental rules overview

Get notified when Erosion Control in Lakewood, CO changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Erosion Control in Nearby Cities

How other cities in Jefferson County handle erosion control.

Arvada, CO
Some Restrictions