Spokane County, WA Environmental Rules: Erosion Control (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Governing section
SCC 9.14.185, Erosion and Sediment Control
Major disturbance threshold
1 acre or 5,000 sq ft impervious
Required plan
Stormwater Pollution Prevention Plan (SWPPP)
Controlling manuals
Spokane Regional Stormwater Manual & SWMMEW
Enforcing office
Spokane County engineer/public works director

Summary

Spokane County requires a stormwater pollution prevention plan and erosion and sediment control best management practices for major land-disturbing activities under SCC 9.14.185, covering projects disturbing an acre or more or adding 5,000 square feet of impervious surface. The county engineer administers and enforces the standard, which applies even when no county permit is required.

These county ordinances apply to unincorporated areas of Spokane County. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

The purpose of the requirements of this chapter is to control soil erosion and sedimentation through the use of temporary and permanent structural as well as non-structural erosion and sediment control (ESC) practices..."Major land-disturbing activity" means a land-disturbing activity greater than or equal to one acre of disturbed area or the creation or addition of impervious surface area greater than or equal to five thousand square feet.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 63).

Full Breakdown

185 of the Spokane County Code sets erosion and sediment control (ESC) standards for land-disturbing activity in the unincorporated county. The chapter applies to all 'major land-disturbing activities,' defined as disturbing one acre or more, or adding 5,000 square feet or more of impervious surface, plus any 'minor land-disturbing activity' that's part of a larger common plan of development or sale or that itself needs a county permit. Applicants must prepare and implement a stormwater pollution prevention plan (SWPPP) using structural and non-structural best management practices (BMPs) consistent with the Spokane Regional Stormwater Manual and the Washington Department of Ecology's Stormwater Management Manual for Eastern Washington, with the stricter of the two controlling any conflict.

The county engineer or public works director, or the director of whichever department issued the underlying permit, administers and enforces the chapter and may enter any permitted or permit-pending site to inspect. Even a major land-disturbing project that needs no county permit still must meet the chapter's performance standards. 020, forest practices under WAC Title 222 (except Class IV conversions from timberland), emergency utility or government work to restore service or reopen a road, and permits with no physical ground disturbance, such as interior remodels or paper land divisions. 185.

Violations & Fines

Willfully damaging, altering or removing stormwater drainage facilities required under the drainage and erosion chapter, or failing to maintain, repair or restore facilities a person is responsible for, is charged as a misdemeanor under the companion penalty section adjoining Section 9.14.185. The county engineer or public works director can also deny, condition or revoke development and approach permits for noncompliance with the erosion and sediment control performance standards.

Frequently Asked Questions

What triggers Spokane County's erosion control requirements?
A 'major land-disturbing activity,' defined in Section 9.14.185(3) as disturbing at least one acre or adding at least 5,000 square feet of impervious surface, triggers the chapter's erosion and sediment control standards, as does any minor disturbance that's part of a larger development plan or that itself requires a county permit.
Do I need a stormwater plan even without a county permit?
Yes, if the project qualifies as a major land-disturbing activity. Section 9.14.185(2)(b) states that such activity remains subject to the chapter's performance standards and enforcement even when Spokane County doesn't require a permit for it, though state or federal permits may still apply.
What manual sets the technical erosion-control standards?
The Spokane Regional Stormwater Manual and the Washington Department of Ecology's Stormwater Management Manual for Eastern Washington both apply, and Section 9.14.185(2)(d)-(e) directs that wherever the two conflict, the more stringent standard controls the best management practices used.

Sources & Official References

Other rules in Spokane County

All Spokane County rules

Compare Spokane County to another location·View the Washington environmental rules overview

Get notified when Erosion Control in Spokane County, WA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Erosion Control in Cities Across Spokane County