Key Facts

SWPPP required
at 1+ acre disturbed
TCEQ notice of intent
required at 5+ acres
Inspection interval
every 14 days minimum
Enforced by
city public works department
Escalation
field notice, then stop work order

Summary

New Braunfels requires every construction site to use best management practices controlling sediment and silt runoff, with a written stormwater pollution prevention plan mandatory once disturbed land reaches one acre.

All operators of construction activities shall use best management practices to control and reduce discharges of sediment, silt, soil, and other materials associated with construction activities to the municipal separate storm sewer system (MS4), waters in the state, and waters of the United States. Operators and owners of construction projects shall adhere to guidelines and best management practices set forth in the city drainage and erosion control design manual. Operators and owners of construction projects shall adhere to erosion and sediment control guidelines set forth in Part III, Section G of the Texas Pollutant Discharge Elimination System (TPDES) General Permit for Stormwater Discharges from Construction Sites (TXR15000) and all other TXR15000 permit requirements associated with construction activity.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 36).

Full Breakdown

Under City Code § 143-7, all operators of construction activity must control and reduce sediment, silt, and soil discharges to the city's storm sewer system and to state and federal waters. Sites disturbing 1 to under 5 acres must file a small construction site notice with public works and prepare a stormwater pollution prevention plan (SWPPP) before work begins; sites of 5 acres or more must also submit a TCEQ notice of intent. Qualified personnel must inspect disturbed areas, storage sites, and control measures at least every 14 days, or every 7 days without a rainfall trigger, and fix problems within 7 days of inspection. Temporary controls come out only after final stabilization.

Violations & Fines

City may issue a field correction notice, then a stop work order if uncorrected; continued noncompliance can bring citations, civil injunctive remedies, and penalties.

Frequently Asked Questions

Does a small backyard project need a stormwater plan in New Braunfels?
Only if it disturbs an acre or more of land. Below that, the general BMP requirement in § 143-7(a) still applies, but no SWPPP or site notice is required.
Who inspects construction sites for erosion control in New Braunfels?
The city public works department and city engineer inspect disturbed areas, storage sites, and control measures, at minimum every 14 days under § 143-7.

Sources & Official References

Other rules in New Braunfels

All New Braunfels rules

Texas rules heatmap·Compare New Braunfels to another location·View the Texas environmental rules overview

Get notified when Erosion Control in New Braunfels, TX changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.