Key Facts

Permit required
Before any land disturbance begins
Stabilization deadline
14 calendar days after work stops
Civil penalty
Up to $32,500 per violation, per day
Misdemeanor fine
$2,500 to $32,500 plus up to 12 months jail
Felony fine (knowing violation)
$5,000 to $50,000, 1-3 years prison
Enforcing office
Director of Public Works, VSMP administrator

Summary

Prince William County will not issue a grading, building or land disturbance permit until the developer has a consolidated stormwater and land disturbance permit backed by an approved erosion and sediment control plan under the county's Design and Construction Standards Manual. Once clearing stops for more than 14 days, exposed soil must be stabilized immediately. Violators face court-ordered civil penalties up to $32,500 per day, plus criminal charges.

These county ordinances apply to unincorporated areas of Prince William County. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

(a)No person shall engage in any land disturbing activity until a consolidated stormwater and land disturbance permit has been issued with the provisions of this article...(3)An erosion and sediment control plan approved in accordance with section 750.00 of the Prince William County design and construction standards manual and this article...(8)Stabilization of disturbed areas must, at a minimum, be initiated immediately whenever any clearing, grading, excavating, or other earth disturbing activities have permanently ceased on any portion of the site, or temporarily ceased on any portion of the site and will not resume for a period exceeding 14 calendar days...Any person who violates any provision of this article or who fails, neglects, or refuses to comply with any order of the director or the court, shall be subject to a civil penalty not to exceed $32,500.00 for each violation within the discretion of the court. Each day of violation of each requirement shall constitute a separate offense.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 46 Update 4).

Full Breakdown

15:27, and folds erosion and sediment control into the same permitting track as stormwater management. 2-30, no person may begin any land disturbing activity, including single-family lot grading, until the director of public works has issued a consolidated stormwater and land disturbance permit. 02, and evidence of state general permit coverage; no grading or building permit follows until fees and a performance bond are posted. 2-31 folds the erosion and sediment control plan into a broader Stormwater Pollution Prevention Plan (SWPPP), which must control runoff volume and velocity, minimize exposed soil and disturbance of steep slopes, and buffer surface waters.

Stabilization of any disturbed area must begin immediately once clearing, grading or excavation has permanently stopped, or temporarily stopped for more than 14 calendar days. 2-45 when a permittee ignores a notice to correct, or an emergency cessation order without advance notice if erosion is causing imminent harm to state waters. This program supersedes the older subdivision-chapter erosion and sediment control language at section 25-14, which still requires plans for subdivision improvements to be approved by the director of planning under the manual.

Violations & Fines

Circuit court civil penalties reach $32,500 per violation per day under section 23.2-46, covering missing state permit registration, no SWPPP, an unapproved erosion and sediment control plan, or improperly installed or maintained controls. Section 23.2-47 makes a willful or negligent violation a misdemeanor punishable by up to 12 months in jail and a fine of $2,500 to $32,500; a knowing violation is a felony carrying one to three years in prison and a $5,000 to $50,000 fine, with a $10,000 minimum fine for corporate defendants, doubled for repeat offenses.

Frequently Asked Questions

Do I need a permit before clearing land in Prince William County?
Yes. Section 23.2-30 bars any land disturbing activity, including grading a single home lot, until the director of public works issues a consolidated stormwater and land disturbance permit backed by an approved erosion and sediment control plan meeting the county's Design and Construction Standards Manual section 750.00.
What happens if grading stops and the ground is left bare?
Section 23.2-31(f)(8) requires stabilization to begin immediately once clearing, grading or excavation has permanently stopped, or temporarily stopped for more than 14 calendar days on any part of the site, unless the director approves an alternative timeline.
What penalties apply for violating erosion control requirements?
Section 23.2-46 authorizes circuit court civil penalties up to $32,500 per violation per day. Section 23.2-47 adds criminal exposure: a misdemeanor with up to 12 months in jail for willful or negligent violations, escalating to a felony with one to three years in prison for knowing violations.
Who administers erosion and sediment control in the county?
The director of public works or a designee, acting as administrator of the Virginia Stormwater Management Program under section 23.2-29, reviews plans, inspects active sites, and can issue stop work or emergency cessation orders under section 23.2-45.

Sources & Official References

Other rules in Prince William County

All Prince William County rules

Compare Prince William County to another location·View the Virginia environmental rules overview

Get notified when Erosion Control in Prince William County, VA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.