Santa Barbara County, CA Environmental Rules: Erosion Control (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified August 2026

Key Facts

Governing section
County Code Sec. 14-29
Rainy season
November 1 to April 15
Minimum down drain size
12 inches diameter
Slope planting deadline
Within 30 days of grading completion
Plan review agency
County Public Works / Building Official

Summary

Any grading project in unincorporated Santa Barbara County must have an approved erosion and sediment control plan, or an equivalent state SWPPP, under County Code Sec. 14-29. During the rainy season, November 1 through April 15, no grading can occur unless approved erosion control measures are already in place.

City-specific rules exist: Santa Maria has its own erosion control rules that differ from Santa Barbara County's county-level regulations. If you live in Santa Maria, check the city-specific page instead.

(a)An erosion and sediment control plan shall be required as part of the grading plan and permit requirements. The plan shall incorporate applicable county-approved best management practices. In lieu of the erosion and sediment control plan, the county may accept a SWPPP, prepared for the state, if it contains the requirements of the county's erosion and sediment control plan. ... (d)The erosion and sediment control plan shall specify which erosion control measures necessary to control runoff shall be in place during the rainy season (November 1 through April 15) and which measures shall be in place year round. At a minimum, during the rainy season no grading shall occur unless approved erosion and sediment control measures are implemented. Erosion and sediment control measures shall be in place prior to any grading on hillsides, sloping or mountainous terrain. Measures for non-storm water construction site discharge control shall be implemented year round.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 44 Update 1).

Full Breakdown

Sec. 14-29(a) requires the erosion and sediment control plan to identify practices to retain sediment onsite, such as sediment basins and silt traps with a maintenance schedule, runoff and slope-stabilization methods including mulching or hydroseeding, vegetative planting rates and schedules, and precautions to stop vehicles tracking soil onto public streets. The plan must also address best management practices for non-storm-water pollutants like discarded building material, sanitary waste, and washout from drywall, grout, plaster, mortar or concrete, which must be collected and removed rather than allowed to run off, per Sec.

14-29(a)(5). A master drainage plan is required for every grading permit, with detailed design standards under Sec. 14-29(c): diverting terraces at least three feet wide and one foot deep atop steep cut slopes, berms at least one foot high atop fill slopes, down drains at least twelve inches in diameter, and all outlet structures into public roads or flood control facilities approved by the county public works department. Sec. 14-27 separately requires any man-made slope over three feet high to be planted to control erosion within thirty days of finishing grading.

Under Sec. 14-29(d), erosion and sediment control measures must be in place before any grading on hillsides or sloping terrain, and non-storm-water discharge controls apply year-round, not just in the rainy season.

Violations & Fines

Grading without the required erosion and sediment control measures is enforced the same as any other Chapter 14 violation: the building official can issue a stop-work order under Sec. 14-20, and a violation can be filed as an infraction, up to $500 for repeat offenses within a year, or as a misdemeanor carrying a fine of $500 to $25,000 and up to six months in county jail under Sec. 14-33, with each day of noncompliance a separate offense.

Frequently Asked Questions

Do I need an erosion control plan for a Santa Barbara County grading project?
Yes, if the project needs a grading permit. Sec. 14-29(a) requires an approved erosion and sediment control plan, or an accepted state SWPPP covering the same elements, before grading can proceed under the county's Grading Code.
Can grading continue during the rainy season?
Only with approved erosion and sediment control measures already in place. Sec. 14-29(d) bars grading during the rainy season, November 1 through April 15, unless those measures are implemented, and requires them in place before any hillside grading regardless of season.
Who approves drainage designs for a grading project?
The building official approves most drainage devices under Sec. 14-29(c), but outlets discharging into public roads, streets or flood control facilities need county public works department approval, and natural watercourse designs need sign-off from the flood control and water conservation district.

Sources & Official References

Other rules in Santa Barbara County

All Santa Barbara County rules

California rules heatmap·Compare Santa Barbara County to another location·View the California environmental rules overview

Get notified when Erosion Control in Santa Barbara County, CA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Erosion Control in Cities Across Santa Barbara County