Key Facts

Freeboard above BFE
2 feet minimum, lowest floor
Fill in flood fringe
over 50 cu. yds. needs CLOMR-F
Certificate required
FEMA Elevation Certificate before final inspection
Governing code
2025 CRC § R306, locally amended
Enforcing agency
Santa Cruz County Building Official

Summary

In unincorporated Santa Cruz County, new and substantially improved buildings in mapped flood hazard areas must have their lowest floor elevated at least 2 feet above the base flood elevation, and an elevation certificate must go to the Building Department before final inspection.

These county ordinances apply to unincorporated areas of Santa Cruz County. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

R306.2.1 Elevation requirements. 1. Buildings and structures in flood hazard areas shall have the lowest floor elevated at least 2 feet (610 mm) above the base flood elevation. 2. In areas of shallow flooding (AO Zones), buildings and structures shall have the lowest floor elevated at least 2 feet (610 mm) above the highest adjacent grade plus the depth number specified in feet on the FIRM, or at least 2 feet (610 mm) if a depth is not specified. 3. Basement floors that are below grade on all sides shall be elevated at least two feet above the base flood elevation.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: rev 5004302; v11 updated 2026-05-19; through 05-19-2026).

Full Breakdown

220(C)(5), requires that buildings and structures in flood hazard areas have the lowest floor elevated at least 2 feet above the base flood elevation, a 2-foot freeboard margin above the FEMA minimum. In AO Zones of shallow flooding, the lowest floor must sit at least 2 feet above the highest adjacent grade plus the FIRM depth number, or 2 feet if none is specified; non-residential structures that cannot be elevated must be floodproofed to the same 2-foot standard. Basement floors below grade on all sides face the identical 2-foot-above-BFE rule.

6 requires a FEMA Elevation Certificate (Form 086-0-33) submitted to the Department before any final inspection on a new or substantially improved structure. 3, including a County 'V Zone Cert' and, at final inspection, a Final V-Zone Certificate or Final Non-residential Floodproofing Design Certificate. Placing more than 50 cubic yards of fill in the flood fringe requires an engineered grading plan, an equal volume removed elsewhere on or adjacent to the site, and a FEMA Conditional Letter of Map Revision-Fill (CLOMR-F) before the building permit issues. 13.

Violations & Fines

Building without the required freeboard elevation, without a compliant CLOMR-F for fill placement, or without submitting the FEMA Elevation Certificate blocks final inspection and occupancy approval from the Building Official. Uncertified construction in a flood hazard area is treated as noncompliant and can be red-tagged until documentation demonstrating compliance with Section R306.2 is provided.

Frequently Asked Questions

How much above the base flood elevation must my house be built in Santa Cruz County?
At least 2 feet above the base flood elevation for the lowest floor, per Section R306.2.1 as amended by SCCC § 12.10.220. That 2-foot freeboard applies to A Zones, AO shallow-flooding zones, and basements alike, and non-residential floodproofing must match the same 2-foot margin above the FIRM depth number.
What paperwork does the County want after I frame the lowest floor?
Section R306.2.5 requires documentation verifying the elevation before you can continue vertical construction, and Section R306.2.6 requires a finished-construction FEMA Elevation Certificate (Form 086-0-33) delivered to the Department before your final inspection is scheduled.
Can I add fill dirt to raise my lot out of the flood fringe?
Only under conditions in Section R306.2.7: an engineered grading plan, an equal volume of soil removed from the flood fringe nearby, the minimum fill necessary, the site raised at least 1 foot above base flood elevation, and a FEMA Conditional Letter of Map Revision-Fill obtained before your building permit is issued.

Sources & Official References

Other rules in Santa Cruz County

All Santa Cruz County rules

California rules heatmap·Compare Santa Cruz County to another location·View the California environmental rules overview

Get notified when Flood Elevation Requirements in Santa Cruz County, CA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Flood Elevation Requirements in Cities Across Santa Cruz County