Tulare County, CA Environmental Rules: Flood Elevation Requirements (2026)
Key Facts
- Standard used
- California Building Code and ASCE 24, Chapter 2
- Zone A fallback elevation
- At least 2 feet above highest adjacent grade or DFE
- Certification required by
- Registered civil engineer or land surveyor
- Verified by
- County Surveyor before occupancy permit
- Nonresidential option
- Dry floodproofing under ASCE 24 Section 6.2
Summary
New construction and substantial improvements in unincorporated Tulare County flood zones must have the lowest floor elevated to the minimum set by the California Building Code and ASCE 24. When no base flood elevation exists on the flood map (Zone A), the county can require elevation to at least two feet above the highest adjacent grade or the design flood elevation, whichever is higher.
If the Planning and Development Director and Public Works Director determine that it is unreasonable to determine the base flood elevation pursuant to Section 7-27-1100(b) then the Planning and Development Director and Public Works Director may require that any new construction or substantial improvement of any structures defined in ASCE 24 shall have the bottom of the lowest floor, including basement, elevated to: a height of at least two feet above the highest adjacent grade or DFE, whichever is higher, found in Chapter 2 of ASCE 24.
Full Breakdown
Section 7-27-1180 sets the elevation and floodproofing standards for Chapter 27. Subsection (a) requires new construction and substantial improvement of any structure to conform to the California Building Code and ASCE 24, with the bottom of the lowest floor, including any basement, elevated per the minimum requirements in Chapter 2 of ASCE 24; before an occupancy permit issues, a registered civil engineer or land surveyor must certify the elevation and the County Surveyor must verify it. Subsection (b) requires structures in Zone AO to be elevated to or above the depth number shown on the Flood Insurance Rate Map, measured from the highest adjacent grade.
Subsection (c) addresses Zone A parcels where the map does not list a base flood elevation or depth number: the elevation must first be determined using the methods in Section 7-27-1100(b), and if the Planning and Development Director and Public Works Director find that unreasonable, the Directors may instead require the lowest floor be elevated to at least two feet above the highest adjacent grade or the Design Flood Elevation, whichever is higher. 2 under subsection (d), and elevation certification must be filed at three stages: before permit issuance, once the pad or foundation forms are erected, and before the occupancy permit is released.
Section 7-27-1185 further requires the certification to occur at the point where footings are set and the slab poured, on penalty of a stop-work order for failure to submit it, and allows a Letter of Map Amendment where fill was used to raise a structure above the base flood elevation.
Violations & Fines
Failure to meet the elevation and certification requirements of Section 7-27-1180 triggers a stop-work order under Section 7-27-1185(a) and leaves the structure without a required elevation certificate, which Section 7-27-1010's definition of "Violation" presumes noncompliant until documentation is provided. Under Section 7-27-1375, any Chapter 27 violation is an infraction punishable under Section 125 of the Ordinance Code, with each day treated as a separate offense, and Section 7-27-1370 declares a noncompliant structure a public nuisance subject to abatement.
Frequently Asked Questions
How much freeboard does Tulare County require above the base flood elevation?
Who has to certify my home's flood elevation?
Can a commercial building skip the elevation requirement?
What happens if I don't submit an elevation certificate?
Sources & Official References
Other rules in Tulare County
California rules heatmap·Compare Tulare County to another location·View the California environmental rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.