Key Facts

Freeboard added to BFE
Two feet
No-BFE default elevation
Two feet above highest adjacent grade
Applies to
New construction and substantial improvements
Certification required
Pre-construction, post-reference-level, final as-built
Administering official
Floodplain administrator
Maximum fine
$50.00 or 30 days, or both

Summary

Onslow County requires new and substantially improved buildings in special flood hazard areas to be elevated to two feet above the base flood elevation, or two feet above the highest adjacent grade where no BFE has been set, under the Flood Damage Prevention chapter.

These county ordinances apply to unincorporated areas of Onslow County. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

Regulatory flood protection elevation means the elevation, in relation to mean sea level, to which the reference level of all structures and other development located within special flood hazard areas must be protected. Where base flood elevations (BFEs) have been determined, this elevation shall be the BFE plus two feet of freeboard. Where no BFE has been established, this elevation shall be at least two feet above the highest adjacent grade. ... (1)Residential construction. New construction or substantial improvement of any residential structure (including manufactured homes) shall have the reference level, including basement, elevated no lower than the regulatory flood protection elevation, as defined in section 7-5 of this chapter.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 10).

Full Breakdown

Sec. 7-5 defines the regulatory flood protection elevation as the elevation to which a structure's reference level must be protected in a special flood hazard area: where FEMA has determined a base flood elevation (BFE), the regulatory elevation is the BFE plus two feet of freeboard; where no BFE has been established, it is at least two feet above the highest adjacent grade. That standard is not academic; Sec. 7-97(1) requires that new construction or substantial improvement of any residential structure, including manufactured homes, have its reference level, including any basement, elevated no lower than the regulatory flood protection elevation.

Nonresidential buildings get the same elevation standard under Sec. 7-97(2), though they may floodproof to that elevation instead if a registered engineer or architect certifies the design. The two feet of freeboard exists precisely to buffer against the engineering uncertainty and watershed development changes noted in the Sec. 7-5 definition. Compliance is checked through the certification pipeline in Sec. 7-67(3): an elevation certificate is required before construction starts, another within seven days after the reference level is established, and a final as-built elevation certificate before the county issues a certificate of compliance or occupancy.

The floodplain administrator reviews each certificate and can require corrections before construction proceeds. This freeboard requirement applies to development within Onslow County's mapped special flood hazard areas in the unincorporated county; it does not govern Camp Lejeune's own flood construction standards on federal land.

Violations & Fines

Sec. 7-38 makes any violation of the flood damage prevention chapter, including building below the required freeboard elevation, a misdemeanor punishable by a fine of not more than $50.00 or imprisonment of not more than 30 days, or both, with each day of continued violation a separate offense; the county can also pursue civil or equitable remedies to force correction.

Frequently Asked Questions

How high above the base flood elevation must a new Onslow County home be built?
Sec. 7-5 defines the regulatory flood protection elevation as the base flood elevation plus two feet of freeboard, and Sec. 7-97(1) requires new residential construction to have its reference level elevated no lower than that regulatory elevation.
What if FEMA has not set a base flood elevation for a lot?
Sec. 7-5 provides that where no BFE has been established, the regulatory flood protection elevation defaults to at least two feet above the highest adjacent grade at the site.
When are elevation certificates due during construction?
Sec. 7-67(3) requires one certificate before construction starts, another within seven calendar days after the reference level is established, and a final as-built certificate before the county will issue a certificate of compliance or occupancy.

Sources & Official References

Other rules in Onslow County

All Onslow County rules

Compare Onslow County to another location·View the North Carolina environmental rules overview

Get notified when Flood Elevation Requirements in Onslow County, NC changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.