Key Facts

Enforcing agency
Dept. of Public Works (floodplain administrator)
Elevation standard
Lowest floor at or above base flood elevation
Zone AO/VO minimum
2 ft above highest adjacent grade
First-offense fine
Up to $50, escalating to $250
Variance appeal fee
$100 to Board of Supervisors
Base flood defined as
1% annual chance ('100-year') flood

Summary

Any new construction or substantial improvement in Marin County's mapped special flood hazard areas must have its lowest floor elevated to or above the base flood elevation, per Marin County Code of Ordinances § 23.09.034. The Department of Public Works, acting as floodplain administrator, reviews every permit in flood-prone unincorporated areas before construction begins.

City-specific rules exist: San Rafael has its own flood elevation requirements rules that differ from Marin County's county-level regulations. If you live in San Rafael, check the city-specific page instead.

(c)Elevation and Floodproofing.(1)New construction and substantial improvement of any structure shall have the lowest floor, including basement, elevated to or above the base flood elevation. Nonresidential structures may meet the standards in subparagraph (3) of subsection (c) of this section. Upon completion of the structure, the elevation of the lowest floor, including basement, shall be certified by a registered civil engineer, or licensed land surveyor. Such certification shall be provided to the floodplain administrator.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Municipal Code: Supplement 2026 Update 1).

Full Breakdown

030(4), (27)). The elevation of the completed lowest floor must be certified by a registered civil engineer or licensed land surveyor and filed with the floodplain administrator. 034(c)(2) instead requires the lowest floor to sit above the highest adjacent grade, at least as high as the depth number printed on the Flood Insurance Rate Map, or at least two feet if no depth number is shown. 034(c)(3): a watertight structure below the BFE with components able to resist hydrostatic and hydrodynamic loads, certified by a registered engineer or architect.

033 requires the Department of Public Works to review every application for construction, grading, dredging, paving, drilling or manufactured-home placement inside a flood-prone area and to collect the proposed lowest-floor elevation. 033(d)(3)). 033(d)(5)). 038: no fill, new construction or substantial improvement is allowed unless a registered civil engineer certifies it will not raise flood levels during the base flood discharge.

Violations & Fines

Violating Chapter 23.09 is an infraction under § 23.09.050: a fine up to fifty dollars for a first offense, up to one hundred dollars for a second violation of the same rule within a year, and up to two hundred fifty dollars for each further violation, with every day of continued noncompliance charged as a separate offense. The county can also treat the violation as a nuisance and abate it under Chapter 1.05. A structure built without the required elevation certificate is presumed noncompliant under § 23.09.030(40) until the paperwork is produced.

Frequently Asked Questions

Who enforces Marin County's flood elevation rules in the unincorporated area?
The Department of Public Works administers Chapter 23.09 as the floodplain administrator. Under § 23.09.033, its staff reviews every building, grading or manufactured-home permit proposed within a mapped flood-prone area, requires the proposed lowest-floor elevation before approval, and keeps the resulting elevation certificates on file for flood insurance purposes.
Can I get a variance from the elevation requirement?
Yes, but only on narrow grounds. Section 23.09.040 lets the Board of Supervisors grant a variance for historic structures or where the applicant shows good cause and exceptional hardship, and never within a designated floodway if it would raise flood levels. An appeal or variance request costs a $100 fee.
What if my parcel has no published base flood elevation?
Section 23.09.033(d)(4) directs the floodplain administrator to obtain and use the best available federal, state or other base flood elevation and floodway data to review the permit, rather than treat the parcel as unregulated.

Sources & Official References

Other rules in Marin County

All Marin County rules

California rules heatmap·Compare Marin County to another location·View the California environmental rules overview

Get notified when Flood Elevation Requirements in Marin County, CA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Flood Elevation Requirements in Cities Across Marin County