Orange County, FL Environmental Rules: Flood Elevation Requirements (2026)
Key Facts
- Elevation standard
- 48 in. above grade or BFE + 1 ft, whichever is greater
- Applies to
- Manufactured homes placed, replaced, or substantially improved
- Anchoring
- Over-the-top and frame ties at each corner (§ 19-113)
- Enforcement
- Code enforcement board or special master, Ch. 11
- Variance body
- Development Review Committee, written insurance-cost notice required
- Geographic scope
- Unincorporated Orange County only
- Source ordinance
- Ord. No. 2021-37, § 1, adopted 9-14-21
Summary
In unincorporated Orange County, a manufactured home that is placed, replaced, or substantially improved in a flood hazard area must have the bottom of its frame elevated to at least 48 inches above grade or one foot above base flood elevation, whichever is higher. The Floodplain Administrator enforces the standard under Code § 19-114.
Manufactured homes that are placed, replaced, or substantially improved shall be elevated such that the bottom of the frame is at or above forty-eight (48) inches above grade or base flood elevation plus one (1) foot, whichever is greater.
Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 128).
Full Breakdown
Chapter 19 of the Orange County Code sets the county's floodplain management program, and Article II, Division 4 fixes the elevation standard for manufactured homes. Under Section 19-114, any manufactured home that is placed, replaced, or substantially improved in a flood hazard area must have the bottom of its frame at or above 48 inches above grade, or base flood elevation (BFE) plus one foot of freeboard, whichever produces the higher floor. BFE itself is defined in Section 19-5 as the elevation of the base flood, including wave height, relative to the datum shown on the FEMA Flood Insurance Rate Map.
The same one-foot-above-BFE freeboard standard recurs elsewhere in the chapter: accessory structures below BFE (Section 19-92) must still keep mechanical, plumbing and electrical systems at BFE plus one foot, and agricultural structures granted a wet-floodproofing variance (Section 19-70(2)) must elevate utility equipment the same one foot above BFE. 2 (Section 19-115). A property owner who cannot meet the elevation standard may apply to the Development Review Committee (DRC) for a variance. Before granting one, Section 19-69(4) requires the Floodplain Administrator to give written notice stating the gap between BFE and the proposed lower floor elevation and warning that federal flood insurance premiums rise accordingly, up to $25 per $100 of coverage.
This rule applies only in the unincorporated county; manufactured homes inside Orlando, Winter Park, Apopka, Ocoee, Winter Garden, Maitland and the county's other municipalities fall under each city's own floodplain code, not Chapter 19.
Violations & Fines
Failure to meet the elevation and anchoring standards is punishable under Section 1-9 and may be prosecuted before the county's code enforcement board or a special master under Chapter 11, with each day of noncompliance treated as a separate offense. Under Section 19-73 a violator is also liable for the county's enforcement costs, including attorneys' fees, plus reinspection fees set by Board of County Commissioners resolution to confirm the violation was corrected.
Frequently Asked Questions
How high must a manufactured home be elevated in Orange County's flood zones?
Does this elevation rule apply to a manufactured home in Orlando?
What happens if a manufactured home isn't elevated enough?
Can I get a variance from the 48-inch elevation requirement?
Sources & Official References
Other rules in Orange County
Florida rules heatmap·Compare Orange County to another location·View the Florida environmental rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.