Paulding County, GA Environmental Rules: Flood Elevation Requirements (2026)
Key Facts
- Residential freeboard
- 3 ft above base flood elevation
- Nonresidential freeboard
- 1 ft above base flood elevation
- Manufactured home pier option
- 36 in. minimum above grade
- Certification required
- Licensed engineer or architect
- Enforcing agency
- Community Development Director
Summary
New homes built inside Paulding County's future-conditions floodplain must have their lowest floor, including any basement, elevated at least three feet above the base flood elevation or one foot above the future-conditions flood elevation, whichever number is higher.
New construction of principal residential structures shall not be allowed within the limits of the future-conditions floodplain unless all requirements of sections 10.4.3, 10.4.4 and 10.4.5 have been met. If all of the requirements of sections 10.4.3, 10.4.4 and 10.4.5 have been met, all new construction shall have the lowest floor, including basement, elevated no lower than three feet above the base flood elevation or one foot above the future-conditions flood elevation, whichever is higher.
Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 35).
Full Breakdown
The freeboard standard sits in the county's building standards for structures within the future-conditions floodplain. 5; only then can new construction or a substantial improvement of a principal residential structure proceed, with the lowest floor set no lower than three feet above the base flood elevation or one foot above the future-conditions flood elevation, whichever is higher. 1(5)(a) formula of one square inch of opening per square foot of enclosed area, with opening bottoms no higher than one foot above grade. Nonresidential structures get a lower freeboard floor: one foot above the base flood elevation, or they may be floodproofed watertight to that same elevation instead of elevated, with the design certified by a licensed professional engineer or architect on a FEMA floodproofing certificate. Manufactured homes follow the residential three-foot standard, or the chassis can instead rest on reinforced piers at least 36 inches above grade. 3.
Violations & Fines
Building below the required freeboard elevation is treated as noncompliant new construction under the Flood Damage Prevention Ordinance: the Community Development Director can withhold a certificate of occupancy, issue a stop-work order, or revoke the permit until an as-built elevation certificate confirms the lowest floor meets the three-foot (or one-foot nonresidential) standard, with civil penalties of up to $1,000 per day for uncured violations.
Frequently Asked Questions
How high above base flood elevation must a new house be built in Paulding County?
Is the freeboard requirement different for commercial buildings?
Can I use enclosed space below the elevated floor for storage?
Sources & Official References
Other rules in Paulding County
Compare Paulding County to another location·View the Georgia environmental rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.