Coconino County, AZ Environmental Rules: Stormwater Management (2026)
Key Facts
- General hearing permits
- storm drainage report required (§5.1.C.1.J)
- Utility-scale renewable projects
- LID standards required (§3.19.E.4)
- Technical standard
- County Drainage Design Criteria Manual
- Biomass facilities
- separate ADEQ stormwater control permit
- Completeness review
- 60 calendar days (A.R.S. § 11-1605)
Summary
Coconino County's zoning ordinance requires a preliminary storm drainage report for any permit that goes to public hearing, and layers on numeric low-impact-development standards for utility-scale energy projects. Section 5.1.C.1.J covers general drainage submittals; Section 3.19.E.4 sets the county's most detailed stormwater control requirements.
The project shall be planned with low impact development stormwater management techniques, as outlined in the Drainage Design Criteria Manual, to capture and infiltrate stormwater and rainwater. Biomass Energy Installations shall obtain a stormwater control permit for the facility, including materials stockpiles, from the Arizona Department of Environmental Quality. Additional stormwater controls may be required. ... Plans and/or a preliminary report describing the proposed provisions for storm drainage, sewage disposal, and such other public improvements and utilities as the Director may require in order to give a full evaluation of the project.
Official source re-checked September 7, 2026: the cited page had not changed since it was quoted.
Full Breakdown
J. The Community Development Director decides what level of detail that report needs on a project-by-project basis; the ordinance does not print a single countywide detention or runoff-rate number for ordinary development. The zoning ordinance's most detailed stormwater standard instead applies to Utility Scale Renewable Energy Systems. 4 requires that 'the project shall be planned with low impact development stormwater management techniques, as outlined in the Drainage Design Criteria Manual, to capture and infiltrate stormwater and rainwater,' and that 'Biomass Energy Installations shall obtain a stormwater control permit for the facility, including materials stockpiles, from the Arizona Department of Environmental Quality,' with the county reserving the right to add 'additional stormwater controls' as needed.
Both provisions route back to the same technical reference, the county's Drainage Design Criteria Manual, and to the County Engineer's review authority referenced throughout Chapter 5's permit-submittal sections, meaning drainage adequacy for larger or hearing-level projects is evaluated case by case rather than through a fixed subdivision-wide formula.
Violations & Fines
An incomplete or missing storm drainage report makes a hearing-level application administratively incomplete under Section 5.1.C.1, delaying or blocking the 60-day completeness review the ordinance sets under A.R.S. § 11-1605. For utility-scale renewable projects, failing to obtain the required Arizona Department of Environmental Quality stormwater control permit, or exceeding the Drainage Design Criteria Manual's low-impact-development standards, is a permit-condition violation the county can enforce against under Section 3.19.
Frequently Asked Questions
Does Coconino County have a numeric stormwater detention standard for a new house or business?
What stormwater rules apply to a large solar or wind farm?
Who reviews stormwater plans for a Coconino County permit?
Sources & Official References
Other rules in Coconino County
Compare Coconino County to another location·View the Arizona environmental rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.