Key Facts

TSS reduction required
At least 80%, Sec. 99-202(b)(18)
Total nitrogen reduction
At least 30%, Sec. 99-202(b)(18)
Bacteria load reduction
At least 60%, Sec. 99-202(b)(18)
Applies to
All development/redevelopment, unincorporated county
Administering agencies
Public Works & Stormwater Departments, Sec. 99-206
Appeal deadline
30 days of decision, Sec. 99-213(a)
Max penalty
$1,000 fine or 30 days, Sec. 99-504(b)

Summary

Beaufort County requires new development and redevelopment in the unincorporated county to meet numeric stormwater quality targets: at least an 80 percent reduction in total suspended solids, 30 percent reduction in total nitrogen, and 60 percent reduction in bacteria load, on top of volume control, under its stormwater management ordinance.

These county ordinances apply to unincorporated areas of Beaufort County. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

The stormwater management practices of approved plans shall provide volume control and at least an 80 percent reduction in total suspended solids loads, 30 percent reduction of total nitrogen load, and 60 percent reduction in bacteria load.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 55 Update 1 | Community Development Code: Supplement 16).

Full Breakdown

Sec. 99-200 grounds the article in the county's authority under the South Carolina Constitution, the state legislature, and the federal Clean Water Act. Sec. 99-201 finds that uncontrolled stormwater runoff threatens the county's Outstanding Resource Waters, shellfish harvesting areas, and public health, safety, and welfare, and that development alters watershed hydrology and increases runoff, flooding, and pollutant transport. Sec. " Sec. 99-202(b)(13) ties design criteria to the most current Southern Lowcountry Stormwater Design Manual, and Sec. 99-204 makes the article applicable to all development and redevelopment and any illicit discharges throughout the unincorporated county.

The public works department and a separate stormwater department administer the program under Sec. 99-206, maintaining the design manual's construction-application, closeout, and inspection requirements, while Sec. 99-207 gives administrators power to review, approve, condition, or disapprove stormwater management plans and set application fees. Appeals of an administrator's decision go to the stormwater management utility board under Sec. 99-213, which must be filed within 30 days of the decision or notice of violation.

Violations & Fines

Sec. 99-504 places enforcement jurisdiction with both the Beaufort County Public Works Department and Beaufort County Codes Enforcement, with officers holding full discretion to issue a notice of violation, a stop-work order, or a fine. A conviction for violating the article or an approved stormwater permit is a misdemeanor carrying a penalty not to exceed $1,000.00 or 30 days imprisonment for each violation, with each continuing day treated as a separate violation, and the county attorney may separately pursue civil abatement costs against the responsible party under Sec. 99-503(c)-(d).

Frequently Asked Questions

What water-quality standard must new development in Beaufort County meet?
Sec. 99-202(b)(18) requires approved stormwater management practices to provide volume control along with at least an 80 percent reduction in total suspended solids, a 30 percent reduction in total nitrogen load, and a 60 percent reduction in bacteria load compared to pre-development conditions.
Which projects does the stormwater ordinance cover?
Sec. 99-204 applies the article to all development and redevelopment and to any illicit discharges, and confines its reach to the unincorporated areas of Beaufort County. Municipalities such as Hilton Head Island and Bluffton administer their own stormwater programs.
Who reviews and approves a stormwater management plan?
Under Sec. 99-207, the county's administrators, meaning the public works director, the stormwater manager, and other designees, review, approve, approve with conditions, or disapprove stormwater management plan applications, following criteria in the Southern Lowcountry Stormwater Design Manual referenced in Sec. 99-206.
What happens if a site violates its stormwater permit?
Sec. 99-504 makes violating the article or an approved Beaufort County Stormwater Permit a misdemeanor, with a penalty up to $1,000.00 or 30 days imprisonment per violation, each day counted separately, enforced jointly by Public Works and Codes Enforcement.

Sources & Official References

Other rules in Beaufort County

All Beaufort County rules

Compare Beaufort County to another location·View the South Carolina environmental rules overview

Get notified when Stormwater Management in Beaufort County, SC changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.