Key Facts

Design storm
10-year storm, post-construction velocity
Standard
Discharge velocity capped by table or pre-development rate
Tolerance
Up to 10% above pre-development if reinforced
Governing section
Code § 18-25
Civil penalty
Up to $5,000 per violation
Administered by
Rowan County Planning and Development Dept

Summary

Rowan County limits how fast stormwater can leave a construction site. Code Section 18-25 requires post-construction runoff velocity from the ten-year storm to stay at or below either a maximum permissible velocity table or the site's pre-development velocity, whichever is greater, to protect downstream stream banks and channels from accelerated erosion.

These county ordinances apply to unincorporated areas of Rowan County. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

Intent. Stream banks and channels downstream from any land-disturbing activity shall be protected from increased degradation by accelerated erosion caused by increased velocity of runoff from the land-disturbing activity. ... Persons shall conduct land-disturbing activity so that the post-construction velocity of the ten-year storm runoff in the receiving watercourse to the discharge point does not exceed the greater of:(1)The velocity established by the maximum permissible velocities table set out in subsection (e) of this section; or(2)The velocity of the ten-year storm runoff in the receiving watercourse prior to development.

Full Breakdown

Section 18-25 of the Soil Erosion and Sedimentation Control Ordinance governs stormwater leaving any land-disturbing activity in unincorporated Rowan County. Its stated intent is to protect stream banks and channels downstream from accelerated erosion caused by increased runoff velocity. 0 feet per second for coarse gravel or shale, or the velocity of the ten-year storm in that watercourse before development occurred. If neither limit can be met, the channel to and including the discharge point must be built to withstand velocities up to ten percent above the pre-development rate.

The ordinance lists acceptable ways to meet the standard, including promoting infiltration to offset new impervious surface, using vegetated or roughened swales instead of high-velocity paved channels, installing energy dissipators such as riprap at storm drainage outlets, and upgrading the receiving watercourse itself. Rowan County will excuse a project from this section only where it can be shown the discharge will not create an erosion problem downstream. Compliance is folded into the same erosion and sedimentation control plan review the Rowan County Planning and Development Department conducts under Section 18-52, and the same Chapter 18 civil and criminal penalties apply to a violation.

Violations & Fines

A stormwater outlet violation is enforced the same way as any other Chapter 18 violation: a civil penalty of up to $5,000 per violation, capped at $25,000 for a first-time violator who corrects the damage within 180 days, under Section 18-91. Knowing or willful violations are a Class 2 misdemeanor with a fine up to $5,000, and Rowan County may seek an injunction in Superior Court to stop ongoing discharge damage.

Frequently Asked Questions

What stormwater speed limit applies to a Rowan County construction site?
Section 18-25 caps the post-construction velocity of a ten-year storm's runoff, at the point it discharges into a receiving watercourse, at whichever is greater: the maximum permissible velocity for that material in the ordinance's own table, or the velocity that watercourse carried before development began.
What if my site can't meet the stormwater velocity limit?
The receiving watercourse, up to and including the discharge point, must then be designed and built to withstand velocities up to ten percent higher than the pre-development rate, using measures like riprap energy dissipators, vegetated swales, or an upgraded channel section under Section 18-25(c).
Is there ever an exception to the stormwater outlet rule?
Yes. Section 18-25(d) excuses a project from the velocity standard if it can be demonstrated to Rowan County that the stormwater discharge will not create an erosion problem in the receiving watercourse. That determination is made during the same erosion and sedimentation control plan review the Planning and Development Department conducts under Section 18-52.
Who enforces the stormwater outlet protection rule?
The Rowan County Planning and Development Department reviews stormwater measures as part of every erosion and sedimentation control plan, and a violation of Section 18-25 carries the same Chapter 18 penalties as any other erosion violation: up to $5,000 per civil violation and Class 2 misdemeanor criminal exposure.

Sources & Official References

Other rules in Rowan County

All Rowan County rules

Compare Rowan County to another location·View the North Carolina environmental rules overview

Get notified when Stormwater Management in Rowan County, NC changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.