Newton County, GA Environmental Rules: Stormwater Management (2026)

Significant Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Permit trigger
5,000 sq ft impervious cover or 1+ acre disturbed
Required filing
Stormwater management plan and maintenance agreement
Concept plan threshold
Subdivisions over 50 lots or 10+ acre nonresidential
Enforcing officer
Development Services director
Maintenance bond
2 years or until 75% of certificates of occupancy
Maximum fine
$1,000.00 per day of violation

Summary

Newton County requires a land-disturbance permit before most development in the unincorporated area under Sec. 50-148(a). Projects that create 5,000 square feet or more of impervious cover, or disturb an acre or more, must submit a stormwater management plan, an inspection and maintenance agreement, and applicable review fees before work begins.

These county ordinances apply to unincorporated areas of Newton County. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

(1)New development that involves the creation of 5,000 square feet or more of impervious cover, or that involves other land development activities of one acre or more; ... No owner or developer shall perform any land development activities without first meeting the requirements of this division prior to commencing the proposed activity. Unless otherwise exempted by this division, or granted a waiver to meeting the minimum requirements outlined in the county stormwater LDM, a land-disturbance permit application shall be accompanied by the following items in order to be considered:(1)Stormwater concept plan and consultation meeting certification if required by subsection (b) of this section;(2)Stormwater management plan;(3)Inspection and long-term maintenance agreement;(4)Stormwater tax assessment area, if applicable;(5)Performance bond, if applicable; and(6)Land-disturbance permit application and applicable review fees.

Full Breakdown

Division 4 of Chapter 50, the county's post-construction stormwater management rules, applies under Sec. 50-145 to any new development or redevelopment that creates 5,000 square feet or more of impervious cover, involves one acre or more of land-disturbing activity, qualifies as a hotspot land use regardless of size, or is part of a larger common plan of development even if built in phases. Sec. 50-148(a) bars any owner or developer from performing land-disturbing activity without first meeting the division's requirements: a land-disturbance permit application must include a stormwater management plan, an inspection and long-term maintenance agreement, a stormwater tax assessment area designation if applicable, a performance bond if applicable, and the applicable review fees, unless a concept plan is required first under subsection (b).

Larger or more complex projects, residential subdivisions over 50 lots, non-residential sites disturbing ten acres or more, or sites with 50 percent or more impervious coverage, must go through a stormwater concept plan and consultation meeting before design plans are even submitted. The stormwater management plan itself must be prepared and certified by a registered professional engineer, land surveyor, or landscape architect, per Sec. 50-147. Once a facility is built, the inspection and maintenance agreement recorded against the property binds every future owner, and the county's Development Services director can inspect the facility, and, if it falls into disrepair, perform the necessary work and place a lien on the property for the cost, per Sec.

50-151(e). Developers must also post a maintenance bond guaranteeing stormwater control workmanship for two years, or until 75 percent of certificates of occupancy are issued, per Sec. 50-148(f).

Violations & Fines

Sec. 50-153 lets the director issue a written notice of violation, then a stop work order, withhold certificates of occupancy, or suspend or revoke the land-disturbance permit if remedial measures are not completed. For intentional or flagrant violations, or a failure to cure within the notice period, the director can issue a citation to Newton County Magistrate Court; a conviction carries a fine of up to $1,000.00, with each day of a continuing violation a separate offense.

Frequently Asked Questions

Do I need a stormwater permit to build in unincorporated Newton County?
Yes, if your project creates 5,000 square feet or more of impervious cover or disturbs an acre or more of land, per Sec. 50-145. Sec. 50-148(a) requires a land-disturbance permit application with a stormwater management plan, an inspection and maintenance agreement, and applicable fees before any land-disturbing work can start.
Who has to maintain a stormwater facility after construction in Newton County?
The property owner does, under the recorded inspection and maintenance agreement required by Sec. 50-148(d), which binds every future owner through a covenant on the deed. The Development Services director can inspect the facility and, if maintenance lapses, perform the work and place a lien on the property for the cost.
What is the penalty for stormwater violations in Newton County?
Sec. 50-153 lets the director start with a notice of violation and stop work order, then withhold certificates of occupancy or suspend the permit. For flagrant or uncured violations, the county can issue a magistrate court citation carrying a fine of up to $1,000.00, with each day of continued violation charged as a separate offense.

Sources & Official References

Other rules in Newton County

All Newton County rules

Compare Newton County to another location·View the Georgia environmental rules overview

Get notified when Stormwater Management in Newton County, GA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.