Key Facts

Governing body
Nueces County Commissioners Court
Administering department
Dept. of Public Works
Design storm, drainage structures
100-year event (Table VI-6)
Drainage easement minimum width
30 feet (15 ft each side)
Floodplain construction
Development permit required
Violation
Class B misdemeanor

Summary

Any subdivision plat filed in unincorporated Nueces County must include storm water drainage facilities engineered to Table VI-6's design storm frequencies. The Department of Public Works reviews the design, and drainage easements along natural waterways must run at least 30 feet wide before the Commissioners Court will approve the plat.

City-specific rules exist: Corpus Christi has its own stormwater management rules that differ from Nueces County's county-level regulations. If you live in Corpus Christi, check the city-specific page instead.

Storm water drainage facilities shall be designed and constructed to accommodate the design storm event shown in Table VI-6. ... The storm water drainage facilities shall be designed to: (a) Account for both on-site and off-site storm water, including water entering the subdivision. (b) Honor natural drainage divides. (c) Convey storm water to a stream, channel, or drainageway. (d) Discharge the design flow into an existing facility of sufficient capacity to receive the discharge. (e) Convey the design flow without overtopping or eroding the channel. ... (f) Not adversely affect adjacent or downstream properties. (g) Must conform to applicable County regulations concerning storm water discharge and quality.

Full Breakdown

Under the Subdivision Regulations' Chapter VI Engineering Guidelines, storm water drainage facilities for any new plat outside a municipality must be sized to Table VI-6's design storm event: a 100-year storm for drainage structures and channels, with lower-frequency events set for arterial, collector and local roads. 1 requires the design to account for both on-site and off-site water entering the tract, honor natural drainage divides, discharge into a receiving facility of sufficient capacity, avoid overtopping or eroding the channel, and not adversely affect downstream property.

Any dam included in a subdivision must meet current state dam-safety standards. 4 requires a drainage easement along every natural and constructed drainageway at least 30 feet wide (15 feet each side of the centerline), and the final plat must carry a note keeping the easement clear of fences, buildings and plantings. 5) must be a sealed hydrologic and hydraulic analysis from a Texas-registered engineer. The rule reaches only land being platted outside a city; it is not a standalone stormwater permit program for already-platted lots. Enforcement sits with the Commissioners Court and County Attorney under Chapter I's general enforcement authority.

Violations & Fines

Knowingly or intentionally violating a drainage requirement the Commissioners Court has adopted is a Class B misdemeanor under Section I-4.1. The County Attorney or other prosecuting attorney may also sue to enjoin the violation or to recover the County's cost of completing the required drainage work, under Section I-4.3.

Frequently Asked Questions

Does this drainage rule apply if I'm not subdividing land?
No. Chapter VI's drainage design standards attach to the subdivision platting process for unincorporated Nueces County. An existing, already-platted lot is not independently regulated by this section; floodplain construction is instead controlled through the county's separate Flood Plain Ordinance.
What storm event must a drainage structure in a new subdivision handle?
Table VI-6 sets a 100-year design storm frequency for drainage structures and channels, with lower frequencies (down to 5 years) applying to storm water contained within adjacent ditches on collector roads.
How wide does a drainage easement have to be?
Section VI-4.4 requires a minimum 30-foot easement along every natural or constructed drainageway, 15 feet on each side of the centerline, and it must stay clear of fences, buildings and plantings under a note placed on the final plat.
What happens if a developer ignores the drainage design requirements?
It is a Class B misdemeanor under Section I-4.1, and the County Attorney can go to court to enjoin the violation or recover the County's cost of bringing the drainage work into compliance under Section I-4.3.

Sources & Official References

Other rules in Nueces County

All Nueces County rules

Texas rules heatmap·Compare Nueces County to another location·View the Texas environmental rules overview

Get notified when Stormwater Management in Nueces County, TX changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Stormwater Management in Cities Across Nueces County