Key Facts

Governing title
KCC Title 12, Stormwater Management Ordinance
Applicability
All site development permits, unincorporated county
Standards
Kitsap County Stormwater Design Manual (incorporated)
Repair notice window
30 days before notice of violation
Enforcer
Kitsap County Public Works (KCPW)
Appeal deadline
20 days to request director meeting

Summary

Unincorporated Kitsap County requires a site development activity permit before any construction that involves drainage, under Title 12, the Stormwater Management Ordinance. Work must follow the county's Stormwater Design Manual, and public works can enforce against neglected drainage facilities with civil penalties.

These county ordinances apply to unincorporated areas of Kitsap County. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

The provisions of this title shall apply to all site development activities requiring land use permits and approvals as defined in Chapter 12.08, both public and private, within the bounds of unincorporated Kitsap County. The provisions of Chapter 12.24 (Operation and Maintenance) shall also apply to existing stormwater facilities in unincorporated Kitsap County. The provisions of Chapter 12.30 (Illicit Discharge Detection and Elimination) shall apply to all situations and circumstances throughout unincorporated Kitsap County. No site development activities requiring land use permits and approvals shall be initiated prior to issuance of a site development activity permit.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: rev 4864424; v0 updated 2025-12-08; through 12-08-2025).

Full Breakdown

010. 030, reaches all site development activities requiring land use permits and approvals, both public and private, within unincorporated Kitsap County, and bars any such activity from starting before a site development activity permit is issued. 020 and updated periodically as stormwater technology evolves. 30's illicit discharge prohibitions apply countywide in the unincorporated area, not just to new development. 04 process, but a variance requires proof of severe, unexpected economic hardship documented against six specific factors, including pre-project use, value loss and remaining feasible uses of the site.

100: it may inspect a stormwater facility that is abandoned, neglected or not functioning, and require the property owner to repair or maintain it within 30 days before a formal notice of violation issues.

Violations & Fines

If a property owner ignores a written repair notice within 30 days, KCPW may issue a notice of violation setting out the required corrective action, a deadline, and a civil penalty; unresolved cases go to the county prosecutor to collect the penalty. In emergencies posing a hazard to health, life, property or drainage capacity, the director may act directly and bill the owner for the reasonable cost. Owners can appeal a notice of violation to the director within 20 days and, if unsatisfied, to the Board of County Commissioners within 10 more days under § 12.36.110.

Frequently Asked Questions

Do I need a permit for drainage work in unincorporated Kitsap County?
Yes. KCC § 12.04.030 requires a site development activity permit before starting any site development activity that needs land use permits and approvals, and the work must meet the standards in the county's Stormwater Design Manual referenced in § 12.04.020.
Who enforces stormwater facility maintenance in Kitsap County?
Kitsap County Public Works. Under § 12.36.100 it inspects neglected or malfunctioning facilities, gives the owner 30 days to repair, and can issue a notice of violation with a civil penalty collected through the county prosecutor if the owner does not comply.
Can I get relief from the stormwater manual's technical requirements?
Only in limited circumstances. § 12.04.025 lets the director grant minor technical deviations if they will not cause noncompliance, or the hearing examiner can grant a variance where the requirements impose a severe, unexpected economic hardship documented against several site-specific factors.

Sources & Official References

Other rules in Kitsap County

All Kitsap County rules

Compare Kitsap County to another location·View the Washington environmental rules overview

Get notified when Stormwater Management in Kitsap County, WA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.