Key Facts

Applies to
mapped public water supply watershed only
High-density buffer
minimum 100 feet along perennial waters
Standard buffer
minimum 30 feet along perennial waters
Governing law
Watershed Protection Ordinance, Appendix A, Art. IV
Administered by
watershed administrator / watershed review board
Criminal penalty
up to $500 fine, misdemeanor per NCGS 14-4
Civil penalty option
$50.00 under Section 106

Summary

In the public water supply watershed portions of unincorporated Rutherford County, the Watershed Protection Ordinance requires a vegetative buffer along perennial streams and reservoirs before land can be developed. New development beyond the low-density option needs a 100-foot buffer; other development needs at least 30 feet, and only limited water-dependent or diminutive structures may sit inside it.

These county ordinances apply to unincorporated areas of Rutherford County. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

Sec. 304. - Buffer areas required. (A)A minimum one hundred (100) foot vegetative buffer is required for all new development activities that exceed the low density option; otherwise, a minimum of thirty (30) foot vegetative buffer for development activities is required along all perennial waters indicated on the most recent versions of U.S.G.S. 1:24,000 (7.5 minute) scale topographic maps or as determined by local government studies. Desirable artificial streambank or shoreline stabilization is permitted.(B)No new development is allowed in the buffer except for water dependent structures, other structures such as flag poles, signs and security lights which result in only diminutive increases in impervious area and public projects such as road crossings and greenways where no practical alternative exists. ... ... Sec. 402. - Abatement. ... (C)Where the watershed review board finds a threat to water quality and the public health, safety and welfare, the board shall institute any appropriate action or proceeding to restrain, correct or abate the condition and/or violation.

Full Breakdown

Rutherford County's stormwater and drainage standards are not countywide; they apply only within the public water supply watershed area mapped under the Watershed Protection Ordinance, Appendix A, Article IV, adopted May 15, 1997. Section 304 sets the buffer: a minimum 100-foot vegetative buffer along perennial waters shown on the current USGS 7.5-minute topographic maps applies to new development activities that exceed the low-density option, while a 30-foot buffer applies to everything else. Streambank or shoreline stabilization is allowed inside the buffer, but new development generally is not, except for water-dependent structures such as docks, minor features like flagpoles, signs, and security lights that add only diminutive impervious area, and public projects such as road crossings and greenways where no practical alternative exists; anything permitted inside the buffer must still minimize built-upon area, direct runoff away from surface waters, and use stormwater best management practices.

Subdivision applications within the watershed must, under Section 203(C), describe the proposed stormwater drainage method and provide a system that diverts runoff away from surface waters using best management practices. The watershed administrator, housed in the planning department, reviews and permits development under this ordinance, and the watershed review board, which is the county planning commission sitting in that capacity, hears appeals and grants variances. Under Section 402, the watershed administrator monitors land uses for threats to water quality, reports findings to the review board, and the board can institute action to restrain, correct, or abate a violation once it finds a threat to water quality or public health, safety, and welfare.

Violations & Fines

A violation of the Watershed Protection Ordinance is a misdemeanor under Section 105, punishable in accordance with N.C.G.S. 14-4, with a fine capped at $500.00 per offense and each day of continued violation a separate offense. Section 106 additionally authorizes the board of commissioners to impose a $50.00 civil penalty and to sue to restrain, correct, or abate the violation or prevent occupancy.

Frequently Asked Questions

Does this buffer rule apply everywhere in the county?
Only if the property sits within the mapped public water supply watershed shown on the county's Watershed Protection Map, which the watershed administrator keeps on file. Outside that mapped area, the county has no separate general stormwater or buffer ordinance, since Rutherford County has no countywide zoning code covering drainage on unincorporated land.
When do I need the full 100-foot buffer versus 30 feet?
The wider 100-foot buffer applies to new development that exceeds the low-density option under Section 302, meaning higher-density or higher built-upon-area projects. Lower-intensity development that stays within the low-density thresholds only needs the 30-foot buffer along perennial waters shown on current USGS 7.5-minute topographic maps.
Can I build anything inside the required buffer?
Very little. Section 304(B) allows only water-dependent structures like docks and bulkheads, minor features such as flagpoles, signs, and security lights that add just a diminutive amount of impervious area, and public projects like road crossings or greenways with no practical alternative route. Any permitted activity must still minimize built-upon area and route runoff away from surface waters.

Sources & Official References

Other rules in Rutherford County

All Rutherford County rules

Compare Rutherford County to another location·View the North Carolina environmental rules overview

Get notified when Stormwater Management in Rutherford County, NC changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.