Snohomish County, WA Environmental Rules: Stormwater Management (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Site plan trigger
2,000 sq ft new/replaced hard surface
Full 9-requirement trigger
5,000 sq ft hard surface or 0.75 acre cleared
Land disturbance trigger
7,000 sq ft disturbed
Noncommercial penalty range
$300 to $3,000 base
Commercial penalty range
$600 to $6,000 base
Repeat violation penalty
Base penalty doubled

Summary

Unincorporated Snohomish County requires a stormwater site plan and drainage review once a project adds 2,000 square feet of new or replaced hard surface, or disturbs 7,000 square feet of land, under SCC chapter 30.63A. Discharges that violate water quality standards draw monetary penalties up to $3,000 for residents and $6,000 for businesses under chapter 7.53.

City-specific rules exist: Marysville, Edmonds, Lynnwood, and Everett have their own stormwater management rules that differ from Snohomish County's county-level regulations. If you live in one of those cities, check the city-specific page instead.

Unless an exception under SCC 30.63A.210 applies, new development projects shall comply with minimum requirements 1 through 5 (SCC 30.63A.400 through 30.63A.525) for the new and replaced hard surfaces and the land disturbed if the new development will: (a) Result in or add 2,000 square feet or greater of new, replaced or new plus replaced hard surface area; or (b) Cause land disturbing activity of 7,000 square feet or greater.

View official code

Official source re-checked September 8, 2026: no newer edition of the code had been published (publisher’s edition: current through legislation passed August 12, 2026).

Full Breakdown

54 SCC, together with the county's Drainage Manual, Engineering Design and Development Standards, and the WSDOT Highway Runoff Manual, constitute the county's stormwater regulations, so the rules run across several chapters rather than one page of code. 300: unless an exception applies, a new development project must comply with minimum requirements 1 through 5, covering a stormwater site plan, erosion control, and best management practices, once it adds 2,000 square feet or more of new, replaced or new-plus-replaced hard surface, or causes 7,000 square feet or more of land-disturbing activity.

Projects that add 5,000 square feet of new-plus-replaced hard surface, convert three-quarters of an acre to lawn or landscaping, or convert two and a half acres to pasture must meet all nine minimum requirements, including permanent flow control and treatment facilities built to the county's Drainage Manual. 310, including a 50-percent-of-assessed-value trigger for commercial and industrial remodels. 070. 180 requiring correction of a violation.

Violations & Fines

SCC 7.53.190 lets the director impose a monetary penalty on the person responsible for a discharge violation, scored under the five-criteria matrix in SCC 7.53.192. For noncommercial violations, SCC 7.53.195 sets base penalties from $300 at 0-2 points up to $3,000 at 13 or more points; SCC 7.53.197 sets commercial base penalties from $600 up to $6,000 on the same point scale. Repeat violations or repeat violators double the base penalty, and the county can add its investigation and lab costs on top of the fine, with all responsible parties jointly and severally liable.

Frequently Asked Questions

When does a Snohomish County project need a stormwater site plan?
Once it adds 2,000 square feet or more of new, replaced, or new-plus-replaced hard surface, or disturbs 7,000 square feet of land, under SCC 30.63A.300. Larger projects, at 5,000 square feet of hard surface or three-quarters of an acre of cleared vegetation, must meet all nine minimum requirements instead of just the first five.
What counts as an illegal discharge under the county's stormwater code?
SCC 7.53.070 prohibits discharging anything to a drainage facility, natural drainage system, receiving water or groundwater that is not entirely stormwater, or that violates state water quality or sediment standards, an NPDES permit, or the state's underground injection control program.
How much is the fine for a stormwater violation in Snohomish County?
Base penalties run $300 to $3,000 for a residential violation under SCC 7.53.195 and $600 to $6,000 for a commercial one under SCC 7.53.197, scored on a five-factor point scale in SCC 7.53.192. Repeat violations double the base amount, plus the county's investigation costs.
Which manual do Snohomish County drainage rules point to?
SCC 30.63A.110 authorizes the Snohomish County Drainage Manual, adopted by rule, to supply the technical detail behind chapter 30.63A, and SCC 30.63A.150 makes the chapter control if the manual ever conflicts with it.

Sources & Official References

Other rules in Snohomish County

All Snohomish County rules

Compare Snohomish County to another location·View the Washington environmental rules overview

Get notified when Stormwater Management in Snohomish County, WA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Stormwater Management in Cities Across Snohomish County