Douglas County, CO Environmental Rules: Stormwater Management (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Governing section
Zoning Resolution § 1-2709
Max proposed slope
3:1 (33.3%)
Wall barrier trigger
retaining wall over 30 inches
Building permit trigger
retaining wall over 4 feet
Contour interval cap
2 feet unless approved
CO security if incomplete
115% of unfinished cost

Summary

New development in unincorporated Douglas County must submit a grading and drainage plan under Zoning Resolution § 1-2709, separate from the county's GESC erosion-control plan. It fixes retaining-wall barrier rules, a 3:1 maximum proposed slope, and mandatory labeling of drainage easements, detention basins, and water quality facilities before Engineering Services will approve a site plan.

These county ordinances apply to unincorporated areas of Douglas County. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

§ 1-2709. Grading and Drainage Plan. The grading and drainage plan shall be prepared at the same scale as the landscape plan. Please note that this plan is separate and distinct from the GESC plan required by Engineering Services... 2. Retaining walls in excess of 30 inches in height (as measured from the lowest ground surface adjacent to the wall) used in conjunction with detention areas or ponds, or located adjacent to a pedestrian access or walking surface, shall require permanent barriers, consistent with Building Code height requirements, for the purpose of protecting the public from potential hazards. 3. Development sites are required to balance earthwork quantities on site in accordance with the GESC Manual. 4. Show existing contour lines as dashed lines (screening acceptable), and proposed contour lines as solid lines. The contour interval shall be no more than two feet unless otherwise approved by the staff planner. A. Distinguish existing grades greater than a 4:1 slope (25%). B. Proposed grades shall be no steeper than a 3:1 slope (33.3%). ... 7. Show and label the required drainage easements with detention, water quality facilities, and storm sewer infrastructure.

Full Breakdown

Douglas County splits stormwater review into two linked plans reviewed by Engineering Services: the grading and drainage plan under § 1-2709, and the separate GESC (Grading, Erosion and Sediment Control) plan required for the same project. The drainage plan must be drawn at the same scale as the landscape plan and show every proposed and existing building, wall, walk, and street. Retaining walls over four feet require a structural design and building permit, and any wall over 30 inches next to a detention pond, basin, or pedestrian walkway must include a permanent barrier consistent with Building Code height rules to protect the public.

3%). The plan must also label flow-direction arrows, low and high points, and the drainage easements carrying detention basins, water quality facilities, and storm sewer infrastructure, plus the top-of-wall and bottom-of-wall elevations at 20-foot intervals along retaining walls. Section 1-2712 carries the enforcement hook: before a certificate of occupancy issues, the applicant must submit as-built plans and an engineer's certification that the detention pond and water quality facilities were built to the approved drainage report, and the site must pass a County inspection confirming drainage improvements are installed as approved.

Violations & Fines

A project cannot receive a certificate of occupancy without submitting as-built drainage plans and an engineer's certification that detention ponds and water quality facilities match the approved report, per § 1-2712. If adverse weather blocks installation before a CO request, the county may issue a temporary certificate of occupancy only after the applicant posts security equal to 115% of the unfinished work's cost, and unfinished site improvements must be completed within six months.

Frequently Asked Questions

Is the drainage plan the same as the erosion-control plan in Douglas County?
No. Zoning Resolution § 1-2709 states the grading and drainage plan is separate and distinct from the GESC plan required by Engineering Services, though both are reviewed together and both draw on the same GESC Manual for earthwork balancing standards.
How steep can graded slopes be on a Douglas County site plan?
Proposed grades cannot exceed a 3:1 slope, which is 33.3%, under § 1-2709(4)(B). The plan must also distinguish any existing grade steeper than 4:1 (25%) so reviewers can see where natural slopes already exceed the proposed standard.
Do retaining walls near a detention pond need special protection?
Yes. Any retaining wall over 30 inches high that sits next to a detention area, pond, or pedestrian walkway must include a permanent barrier meeting Building Code height requirements, specifically to protect the public from the drop-off, per § 1-2709(2).
What must happen before a builder gets a certificate of occupancy?
Under § 1-2712, the applicant must submit as-built plans for any detention pond or water quality facility along with an engineer's certification that construction matches the approved drainage report, and a County site inspection must confirm drainage improvements are installed as shown on the approved plan.

Sources & Official References

Other rules in Douglas County

All Douglas County rules

Compare Douglas County to another location·View the Colorado environmental rules overview

Get notified when Stormwater Management in Douglas County, CO changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Stormwater Management in Cities Across Douglas County