Los Angeles County, CA Environmental Rules: Stormwater Management (2026)

Significant Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified August 2026

Key Facts

SWPPP
Required when directed by Building Official; must be approved before grading permit issued
ESCP filing deadline
October 1 annually, if grading won't finish before November 1
BMP installation deadline
October 15 annually
Fine: missing SWPPP (small project)
$50/day (1–10,000 cu yd)
Fine: missing SWPPP (medium)
$250/day (10,001–100,000 cu yd)
Fine: missing SWPPP (large)
$500/day (over 100,000 cu yd)

Summary

All grading in unincorporated LA County must comply with NPDES requirements: best management practices must be installed before grading begins and maintained until permanent drainage is in place, or daily fines up to $500 per day apply.

City-specific rules exist: El Monte, Compton, Carson, South Gate, Pasadena, Santa Clarita, Glendale, Palmdale, Lakewood, Los Angeles, Long Beach, West Covina, Inglewood, Norwalk, Pomona, Santa Monica, Downey, and Lancaster have their own stormwater management rules that differ from Los Angeles County's county-level regulations. If you live in one of those cities, check the city-specific page instead.

J110.8 National Pollutant Discharge Elimination System (NPDES) compliance.

J110.8.1 General.

All grading plans and permits and the owner of any property on which such grading is performed shall comply with the provisions of this Section for NPDES compliance.

All best management practices shall be installed before grading begins or as instructed in writing by the Building Official for unpermitted grading as defined by Section J103.3. As grading progresses, all best management practices shall be updated as necessary to prevent erosion and to control construction-related pollutants from discharging from the site. All best management practices shall be maintained in good working order to the satisfaction of the Building Official until final grading approval has been granted by the Building Official and all permanent drainage and erosion control systems, if required, are in place.

(Ord. 2025-0047 § 81, 2025.)

Source: LA County Code, Title 12 Chapter 12.80 - Stormwater and Runoff Pollution ControlView official code

Full Breakdown

Section J110.8 requires NPDES compliance for all permitted and unpermitted grading projects. The Building Official may require a Storm Water Pollution Prevention Plan (SWPPP) as a condition of any grading permit. If grading will extend past November 1, the owner must file an Erosion and Sediment Control Plan (ESCP) with the county by October 1, with best management practices (BMPs) installed by October 15. BMPs must be maintained 'in good working order' continuously until final grading approval is granted. Failure to submit SWPPP/ESCP or install BMPs triggers escalating daily fines, and the county can enter the property to install controls at the owner's expense.

Violations & Fines

Missing SWPPP or ESCP: $50/day (1–10k cu yd), $250/day (10k–100k cu yd), $500/day (100k+ cu yd). Failing to install BMPs: $100/day (1–10k cu yd), $250/day (10k–100k cu yd), $500/day (100k+ cu yd). Failure to comply with ESCP can be treated as a grading security default.

Frequently Asked Questions

What is a SWPPP and when is it required for a grading project?
A Storm Water Pollution Prevention Plan (SWPPP) identifies best management practices to prevent construction pollutants from leaving your grading site. The Building Official can require one for any grading permit, and the county won't issue the permit until the SWPPP is approved.
What are the annual stormwater obligations if grading continues through the rainy season?
If grading won't be complete before November 1, you must file an Erosion and Sediment Control Plan (ESCP) by October 1 and have all BMPs installed by October 15. The ESCP must be updated annually to reflect current site conditions.
What happens if I don't install stormwater controls on my grading site?
Daily fines of $100–$500 apply depending on project size. The county can also enter your property to install the required BMPs itself and treat the costs as a grading security default chargeable to you.

Sources & Official References

Other rules in Los Angeles County

All Los Angeles County rules

California rules heatmap·Compare Los Angeles County to another location·View the California environmental rules overview

Get notified when Stormwater Management in Los Angeles County, CA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Stormwater Management in Cities Across Los Angeles County