Key Facts

Permit required
Only inside the Floodplain Overlay District
Governing section
Code of Ordinances § 4478
Administrator
Inspector of Buildings, floodplain administrator
Flood zones covered
A, AE, VE, AO, AH, unnumbered A
Penalty
$5-$300 per day, § 1-9
Outside overlay
No citywide fence permit

Summary

New Bedford does not require a permit to build an ordinary residential fence, except within the city's Floodplain Overlay District. Section 4478 of the Code of Ordinances requires a permit for all proposed development in that overlay district and expressly lists fences among the covered work. The Inspector of Buildings administers the program citywide.

4478. Permits are required for all proposed development in the Floodplain Overlay District. The City of New Bedford requires a permit for all proposed construction or other development in the floodplain overlay district, including new construction or changes to existing buildings, placement of manufactured homes, placement of agricultural facilities, fences, sheds, storage facilities or drilling, mining, paving and any other development that might increase flooding or adversely impact flood risks to other properties.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 19).

Full Breakdown

Chapter 9's Floodplain Overlay District sits over every other zoning district and covers the FEMA-mapped Special Flood Hazard Areas, including Zones A, AE, VE, AO and AH (Sections 4460-4482). Within that overlay, Section 4478 requires a permit for "all proposed construction or other development," and the section names fences directly alongside new construction, changes to existing buildings, manufactured homes, agricultural facilities, sheds, storage facilities, and drilling, mining or paving work. Section 4479 requires the applicant to use a checklist of every local, state and federal permit the project needs and to submit the completed checklist demonstrating that all necessary permits have been obtained before proceeding.

Section 4474 designates the city's Inspector of Buildings as the community's floodplain administrator, the official who runs this permit program. Section 4471 states that the floodplain regulations "take precedence over any less restrictive conflicting local laws, ordinances or codes," so the permit duty for a fence inside a mapped flood zone controls even where the general zoning ordinance's fence rules would not otherwise trigger a permit. Section 4460 further ties floodplain development, including fences, to compliance with the state building code's floodplain provisions (currently 780 CMR) and the Department of Environmental Protection's wetlands regulations. 5-foot vision-clearance limit on corner lots at Section 2740, not through a citywide permit requirement.

Violations & Fines

The floodplain sections carry no permit-specific fine, so an unpermitted fence or other development inside the overlay district falls under the Code's general penalty, Section 1-9: a fine of not less than $5.00 and not more than $300.00 for each offense, with every day the violation continues counted as a separate offense. The Inspector of Buildings, as floodplain administrator, enforces the requirement.

Frequently Asked Questions

Do I need a permit to build a fence in New Bedford?
Only if the fence sits inside the city's Floodplain Overlay District. Section 4478 of the Code of Ordinances requires a permit for all proposed development in that district and specifically lists fences among the covered work, along with sheds, storage facilities and manufactured homes. Outside the mapped flood zones, the zoning ordinance does not require a fence permit.
Who administers New Bedford's floodplain fence permits?
The city's Inspector of Buildings, designated under Section 4474 as the community's floodplain administrator. The permit review process, set out in Section 4479, requires the applicant to complete a checklist confirming that every necessary local, state and federal permit for the project has been obtained before work proceeds.
What happens if I put up a fence in the floodplain without a permit?
The Code's general penalty in Section 1-9 applies: a fine of not less than $5.00 and not more than $300.00 for each offense, with every day the violation continues counted as a separate offense. Section 4471 also makes the floodplain rules take precedence over any conflicting, less restrictive local requirement.

Sources & Official References

Other rules in New Bedford

All New Bedford rules

Compare New Bedford to another location·View the Massachusetts fence regulations overview

Get notified when Fence Permit Requirements in New Bedford, MA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Fence Permit Requirements in Nearby Cities

How other cities in Bristol County handle fence permit requirements.

Taunton, MA
Some Restrictions