Okaloosa County, FL Fence Regulations: Retaining Walls (2026)
Key Facts
- Design requirement
- Licensed professional engineer, countywide
- Statute cited
- Chapter 147, Florida Statutes
- Floodway walls
- No rise in base flood elevation allowed
- Coastal high hazard walls
- State/federal authorization plus engineer analysis
- Governing law
- LDC § 6.06.106; § 3.06.16
Summary
Any bulkhead or retaining wall built in unincorporated Okaloosa County must be designed by a professional engineer under LDC § 6.06.106, the same drainage-standards section that requires bridges to meet FDOT and AASHTO specifications. Walls in a regulated floodway or coastal high hazard zone face added review under LDC § 3.06.16.
2.Bridges shall be designed and constructed in accordance with the most recent edition of: FDOT Standards and Specifications, FDOT Structures Design Guidelines, and American Association of State Highway and Transportation Officials (AASHTO) Standard Specifications for Highway Bridges.3.Bulkhead and/or retaining walls shall be designed by the appropriate professional engineer in accordance with Chapter 147, Florida Statutes.
Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 23).
Full Breakdown
LDC § 6.06.106, part of the county's stormwater and drainage design standards, states that 'bulkhead and/or retaining walls shall be designed by the appropriate professional engineer,' the same subsection that requires bridges to follow FDOT Standards and Specifications, FDOT Structures Design Guidelines and AASHTO's bridge specifications. A retaining wall is treated as engineered infrastructure alongside cross drains, storm drains and side drains, not as an ordinary accessory structure a homeowner can build without professional sign-off.
Where a retaining wall sits inside a regulated floodway, LDC § 3.06.16(C) adds a second layer: any retaining wall, sidewalk or driveway that involves placing fill in that floodway must meet the floodway encroachment limits of § 3.06.12(D), which bars authorizing fill or land-disturbing work in a regulated floodway unless an engineering analysis shows it will not raise the base flood elevation at all.
Retaining walls seaward of the coastal construction control line, in a coastal high hazard area (Zone V) or Coastal A Zone, face a third layer under § 3.06.16(G)(1): bulkheads, seawalls, retaining walls and similar erosion-control structures there are permitted only if authorized by the appropriate federal, state or local authority, kept outside the footprint of and not structurally attached to any building, and backed by an analysis from a qualified registered design professional showing no harmful diversion of floodwaters or increase in wave runup that would damage adjacent property. A retaining wall built on Okaloosa Island or along the Destin/Moreno Point coastline is far more likely to trigger this coastal-zone review than one built inland, given how much of the county's Gulf frontage sits within those hazard zones.
Violations & Fines
Building a bulkhead or retaining wall without a professional engineer's design and stamped plans violates LDC § 6.06.106 and can hold up or void the required development order. In a regulated floodway or coastal high hazard zone, a wall built without the floodway encroachment analysis of § 3.06.12(D) or the no-harmful-diversion analysis required under § 3.06.16(G)(1) is not authorized construction and is subject to the county's code enforcement process.
Frequently Asked Questions
Do I need an engineer to build a retaining wall in Okaloosa County?
Are retaining walls treated differently near the Gulf or in a floodway?
What standard governs the engineering itself?
Sources & Official References
Other rules in Okaloosa County
Florida rules heatmap·Compare Okaloosa County to another location·View the Florida fence regulations overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.