Port St. Lucie, FL Filming & Production: Street Closures (2026)
Key Facts
- Permit type
- Street closure permit, Sec. 99.04
- Covers
- Movies, TV shows, documentaries
- Filing window
- 30 to 365 days ahead
- Required plan
- FDOT maintenance-of-traffic plan
- Review timeline
- 10 days to decide
- Appeal
- 5 days to city manager
Summary
Filming a movie, TV show or documentary on a Port St. Lucie street, sidewalk or alley requires the same street closure permit as a parade or festival, issued by the chief of police under Code Sec. 99.04. Productions must file 30 to 365 days ahead with a traffic plan and insurance.
Sec. 99.04. - Permit required. It shall be unlawful for any person to engage in, participate in, aid, form or start any activity, such as a block party; organized competitive event; road festival; parade/procession ; filming of movies, television shows or documentaries; or other special event utilizing a public right-of-way or portion thereof, unless a street closure permit shall have been obtained as provided in this chapter.
Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 103).
Full Breakdown
Sec. 99.04 lists filming of movies, television shows or documentaries alongside block parties, parades and road festivals as activities that cannot use a public right-of-way without a street closure permit; doing so without one is unlawful. A production company applies to the chief of police under Sec. 99.05, filing between 30 and 365 days before the shoot date. The application must give the responsible contact's name and phone number, the exact segment of street, sidewalk or alley to be used, the proposed hours of filming, a maintenance-of-traffic (MOT) plan built to Florida Department of Transportation Design Standards 600 Index Series, and proof of comprehensive liability insurance satisfactory to the city.
Under Sec. 99.07, the chief of police routes the application through public works, parks and recreation, and risk management before approval, and the city can apportion the street for simultaneous production and vehicular use rather than closing it outright. Sec. 99.08 requires a decision within 10 days of filing and written notice within 5 days; a denial must state its reasons and go out by certified mail. A denied applicant can appeal to the city manager within 5 days under Sec. 99.09, and the manager must rule within 72 hours. Sec. 99.14 authorizes the city to require indemnification and added insurance coverage before a production can close a street for filming, and Sec. 99.13 lets the chief of police revoke the permit if conditions are not met.
Violations & Fines
Closing or using a street, sidewalk or alley for filming without a street closure permit violates Sec. 99.04. Chapter 99 sets no dedicated fine, so the general penalty in Sec. 10.99 applies: $50 for a first offense, $200 for a second if paid within 30 days, up to $500 plus costs if contested, and a second-degree misdemeanor under F.S. §§ 775.082-.083 for a third offense.
Frequently Asked Questions
Do student films or small crews need a street closure permit in Port St. Lucie?
What does a filming permit application need to include?
Will the city close the whole street for a film shoot?
Sources & Official References
Other rules in Port St. Lucie