- Governing section
- Waterbury Code § 150.08
- Trigger
- National/state register listing or district
- Waiting period
- 90 days from application receipt
- Adjoining owner notice
- Certified mail within 20 days
- Objection deadline
- 30 days after published notice
- State authority
- Conn. Gen. Stat. §§ 29-404 to 29-408
Summary
Waterbury imposes a 90-day waiting period before issuing a demolition permit for any building listed on, or under consideration for, the National Register or state register of historic places, or located in a registered historic district.
If it is determined that the proposed demolition is subject to delay, the building official or his/her designee shall inform the applicant in writing that a waiting period of 90 days from the date of receipt of the application will be imposed before granting the demolition permit, in accordance with Conn. Gen. Stat. § 29-406(b) as amended from time to time. During the waiting period referred to in this section, the applicant shall take no action toward demolition of the building, structure or part thereof, including, but not limited to, site remediation and asbestos abatement.
Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: 2026 S-8: Supplement contains: Local legislation current through September 8, 2025).
Full Breakdown
08, adopted under Conn. Gen. § 7-148(c)(10)(F) and §§ 29-404 to 29-408, is designed to give preservation advocates, the property owner, and potential purchasers time to find an alternative to demolishing a historic resource. A demolition permit application triggers delay review if the building is on, or under consideration to be put on, the National Register of Historic Places or the state register, or sits within a National Register or state register historic district. If the Building Official determines the delay applies, he must inform the applicant in writing that a 90-day waiting period from the date the application was received will run before any demolition permit is granted, tracking the state deadline in Conn.
Gen. § 29-406(b). During that period the applicant may take no action toward demolition, including site remediation or asbestos abatement. The applicant must also, within 20 days of being told the project is delayed, mail certified notice to all adjoining property owners of record (per the Tax Assessor's records), publish a legal notice in a local newspaper, and post a city-furnished 'notice of intent to demolish' sign on site for the full 90 days; each notice must include the filing date, a photograph of the structure, its address, owner, proposed demolition date and age, and state that objections must be filed with the Building Official within 30 days of publication or the permit may issue once the 90 days run.
Violations & Fines
Demolishing without first obtaining the required permit, or beginning prohibited demolition-related work (including site remediation or asbestos abatement) during the 90-day waiting period, is enforced through the Building Department's general permitting penalties under § 150.99, tied to the city's annual fee schedule under § 41.11.
Frequently Asked Questions
Which buildings in Waterbury trigger the 90-day demolition delay?
Can I start prep work while the 90-day clock is running?
How are neighbors notified of a proposed historic demolition?
Sources & Official References
Other rules in Waterbury
Compare Waterbury to another location·View the Connecticut historic preservation overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.
Historic-Cultural Monuments in Nearby Cities
How other cities in this county handle historic-cultural monuments.