Skip to main content
CityRuleLookup

Jefferson County, AL Hurricane Preparedness: Flood Elevation (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified August 2026

Key Facts

Fill elevation minimum
2 feet above the 100-year flood elevation
Governing section
Subdivision & Construction Regs § 10.20(b)(5)
Reviewing official
Director of Roads and Transportation/County Engineer
Applies to
Unincorporated Jefferson County subdivision plats
Floodway rule
No fill or structures inside the 100-year floodway

Summary

Jefferson County requires subdivision plats submitted for flood-prone land in the unincorporated county to be filled at least 2 feet above the 100-year flood elevation before the Director of Roads and Transportation/County Engineer will approve them. Fill cannot intrude into the 100-year floodway, and no structure may go there, under Subdivision and Construction Regulations Section 10.20(b)(5).

City-specific rules exist: Birmingham has its own flood elevation rules that differ from Jefferson County's county-level regulations. If you live in Birmingham, check the city-specific page instead.

5. Areas of Poor Drainage. Whenever a plat is submitted for an area which is subject to flooding, the Director of Roads and Transportation/County Engineer may approve such subdivision provided that the applicant fills the affected area of said subdivision to an elevation sufficient to place the elevation of streets and lots at a minimum of 2 feet and/or as defined in the adopted Jefferson County Flood Plain Ordinance, above the 100 year flood elevation and provided the fill does not infringe into the 100 year floodway and conforms with Federal Food Insurance Program guidelines. ... The plat of such subdivision shall provide for an overflow zone along the bank of any stream or watercourse in a width which shall be sufficient in times of high water to contain or move the water, and no fill shall be placed in the 100 year floodway nor shall any structure be erected or placed therein.

Full Breakdown

20, "Drainage and Storm Sewers," within the subsection on the nature of storm water facilities. Item 5, "Areas of Poor Drainage," governs any plat submitted for land subject to flooding. The Director of Roads and Transportation/County Engineer may still approve such a plat, but only if the developer fills the affected area so streets and lots sit at least 2 feet above the 100-year flood elevation, or higher if the adopted Jefferson County Flood Plain Ordinance sets a different figure. The fill cannot intrude into the 100-year floodway and must conform with federal flood insurance program guidelines.

The plat must also show an overflow zone along any stream or watercourse bank wide enough to carry or contain flood flows, and no fill or structure is permitted inside the floodway itself. The same section gives the Director separate authority, under item 6, "Flood Plain District," to prohibit subdividing land lying in a stream's floodplain outright when necessary for public health, safety or welfare, and to bar clearing, grading or dumping in preserved floodplain areas except at the Director's discretion. Both provisions apply only within the unincorporated area the county regulations govern; Birmingham and the county's other incorporated cities set their own separate standards.

Because the underlying Jefferson County Flood Plain Ordinance and the county's floodplain maps exist on file only as scanned documents without a searchable text layer, applicants should confirm the current base flood elevation and any figure higher than the 2-foot floor directly with the Department of Land Planning & Development Services before finalizing fill design.

Violations & Fines

A plat that does not meet the 2-foot fill standard, or that places fill or a structure inside the 100-year floodway, will not receive final approval from the Director of Roads and Transportation/County Engineer, who can withhold plat approval indefinitely until the deficiency is corrected. Because Section 10.20 sits within the plat-approval chapter, noncompliance blocks recording of the subdivision rather than triggering a standalone fine, and the applicant's engineer must resubmit drainage and fill data for review before the plat advances.

Frequently Asked Questions

How much fill above the flood elevation does Jefferson County require before approving a subdivision plat?
At least 2 feet above the 100-year flood elevation, per Subdivision and Construction Regulations Section 10.20(b)(5), though the adopted Jefferson County Flood Plain Ordinance can require more. The fill must raise streets and lots above that line without pushing fill into the 100-year floodway, and it applies to plats submitted for land in the unincorporated county.
Who decides whether a flood-prone subdivision plat gets approved in Jefferson County?
The Director of Roads and Transportation/County Engineer reviews plats submitted for areas subject to flooding and may approve them only once the 2-foot fill standard and floodway restrictions in Section 10.20(b)(5) are met, with supporting engineering data supplied by the developer's engineer.
Can a builder place fill or a structure inside the 100-year floodway in Jefferson County?
No. Section 10.20(b)(5) states no fill shall be placed in the 100-year floodway, nor shall any structure be erected or placed there, and the plat must reserve an overflow zone along the stream bank wide enough to carry high water.

Sources & Official References

Other rules in Jefferson County

All Jefferson County rules

Compare Jefferson County to another location·View the Alabama hurricane preparedness overview

Get notified when Flood Elevation in Jefferson County, AL changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Flood Elevation in Cities Across Jefferson County