Skip to main content
CityRuleLookup

Irondequoit, NY Hurricane Preparedness: Flood Elevation (2026)

Significant Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified October 2026

Key Facts

Applies to
Zones V1-V30, VE, V and Coastal A
Elevation
Bottom of lowest supporting member at or above two feet above BFE
Foundation
Pilings, columns or shear walls; no spread footings or fill
Pile spacing ratio
Not less than 8:1 spacing to diameter
Breakaway walls
Certified design if strength exceeds 20 pounds per square foot
Maximum penalty
$250 fine or 15 days, or both

Summary

In the Town of Irondequoit, New York, new and substantially improved residential structures in Zones V1-V30, VE, V and Coastal A must stand on pilings, columns or shear walls with the bottom of the lowest horizontal supporting member at or above two feet above base flood elevation. Section 136-18 also bars spread footings and fill for structural support.

The following standards, in addition to the standards in § 136-15A, Coastal High Hazard Areas and Coastal A Zones, and § 136-15B, Subdivision and development proposals, and § 136-16, Standards for all structures, apply to new and substantially improved residential structures located in areas of special flood hazard shown as Zones V1-V30, VE, V, or Coastal A on the community's Flood Insurance Rate Map designated in § 136-6. A. Elevation. New construction and substantial improvements shall be elevated on pilings, columns or shear walls such that the bottom of the lowest horizontal structural member supporting the lowest elevated floor (excluding columns, piles, diagonal bracing attached to the piles or columns, grade beams, pile caps and other members designed to either withstand storm action or break away without imparting damaging loads to the structure) is elevated to or above two feet above base flood elevation so as not to impede the flow of water.

Full Breakdown

Section 136-18 of the Town of Irondequoit Code is the coastal counterpart to § 136-17. It covers residential construction and substantial improvements in the areas of special flood hazard shown as Zones V1-V30, VE, V or Coastal A on the Flood Insurance Rate Map named in § 136-6, and it stacks on top of § 136-15A, § 136-15B and the standards for all structures in § 136-16.

The elevation rule measures to the bottom of the lowest horizontal structural member that supports the lowest elevated floor, ignoring columns, piles, bracing, grade beams, pile caps and members built to break away. Structural design must consider wind and water loads acting simultaneously during the base flood. Spread footings and fill material cannot provide structural support for a new building or a substantial improvement.

The piling rules are specific. The design ratio of pile spacing to pile diameter cannot be less than 8:1 for individual piles, and wood piles sit no more than 12 feet on center under load-bearing sills, beams or girders. Minimum penetration is an elevation of five feet below mean sea level if the base flood elevation is +10 msl or less, and at least 10 feet below msl if it is greater. Round timber piles need an eight-inch tip diameter, and reinforced concrete piles need 28-day compressive strength of not less than 5,000 pounds per square inch. Toe nailing as a principal connection method is not permitted.

The permit side sits in Article IV. Section 136-13 requires certified designs for any breakaway wall with design strength in excess of 20 pounds per square foot, and § 136-14D(2) requires a certificate of elevation for the bottom of the lowest structural member once the lowest floor is placed. Work that proceeds before the certificate is approved is at the permit holder's risk.

Violations & Fines

Section 136-9 applies. A violation of Chapter 136, including a breach of any permit condition, is punishable on conviction by a fine of no more than $250, imprisonment for not more than 15 days, or both, and each day of noncompliance is a separate offense. The administrator can issue a stop-work order under § 136-14F for noncompliant work, and a structure without an approved variance is declared noncompliant and reported to FEMA.

Frequently Asked Questions

How high must a coastal-zone home be elevated in the Town of Irondequoit?
In Zones V1-V30, VE, V and Coastal A, the bottom of the lowest horizontal structural member supporting the lowest elevated floor must be at or above two feet above base flood elevation. Section 136-18A requires the structure on pilings, columns or shear walls so floodwater can pass beneath it.
Can I use fill or a spread footing for a new coastal-zone building?
No. Section 136-18C(2) states that spread footings and fill material shall not be used for structural support of a new building or substantial improvement of an existing structure in these zones. Pilings or column foundations anchored against flotation, collapse and lateral movement are the printed alternative.
Does a certificate have to be filed after the lowest floor is placed?
Yes. Under § 136-14D(2), once the lowest floor of a new or substantially improved structure is placed, the permit holder submits a certificate of elevation of the bottom of the lowest structural member, prepared by or under a licensed land surveyor or professional engineer. Further work before approval is at the permit holder's risk.
What does the Town require for a breakaway wall?
Section 136-13 requires designs and specifications, certified by a licensed professional engineer or architect, for any breakaway wall with a design strength in excess of 20 pounds per square foot in these zones where base flood elevations are available. Those designs go in with the floodplain development permit application.

Sources & Official References

Other rules in Irondequoit

All Irondequoit rules

New York rules heatmap·Compare Irondequoit to another location·View the New York hurricane preparedness overview

Get notified when Flood Elevation in Irondequoit, NY changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.